Developer seeks to extend Long Thanh International Airport’s completion deadline to 2027 or 2028

The Airports Corporation of Vietnam (ACV) has proposed extending the deadline for completing the first phase of Long Thanh International Airport to 2027 or 2028 because some parts of the project will remain unfinished this year.
At a meeting with Standing Deputy Prime Minister Pham Gia Tuc on Wednesday, ACV said construction on the project’s third component, which covers essential airport facilities, was 88.6% complete. Disbursements had reached 57% of the contract value.
ACV, the airport’s developer, said it could not complete the entire component by the contractual deadline this year. It expects construction or test runs under several major contracts to wrap up in June 2027, including those for the passenger terminal, the first cargo terminal, the parking garage and the airport management system.
It identified several obstacles. Some materials and equipment differed from contract specifications in manufacturer, brand, type, source or place of origin.
The items were ordered, supplied and installed before ACV approved the changes and the parties signed contract amendments.
Some facilities were built and accepted in accordance with approved construction drawings that differed from the approved technical designs. The technical designs have yet to be amended to reflect those changes.
Some facilities were constructed before the construction drawings were approved.
ACV said these issues must be resolved before the completed works can be formally accepted and the airport licensed to operate.
![]() |
|
Long Thanh International Airport in southern Dong Nai province, November 2026. Photo by VnExpress/Quynh Tran |
Given the progress on the third and fourth components, ACV asked the government to direct the Ministry of Construction to review the schedules for all components and report to the relevant authorities so they can consider extending the deadline for the first phase to 2027 or 2028.
The proposal marks a change from late October, when ACV said it expected Long Thanh airport to begin operations at midnight at the start of Dec. 24, initially handling a maximum of about 366 flights a week.
At the meeting, Deputy Minister of Construction Pham Minh Ha asked ACV to review the changes during construction.
For materials and equipment that differed from contract specifications, he called for a review of their value and cost, along with quality testing and an assessment of whether they met technical requirements. ACV is responsible for arranging the quality tests.
Deputy Minister of Justice Nguyen Thanh Tu asked ACV to specify when it could complete the project.
Nguyen Cong Long, general director of Vietnam Air Traffic Management Corporation, said some remaining work on the second component depended on the completion of infrastructure under the third. He called for priority to be given to finishing technical facilities and connecting the infrastructure so that air traffic management systems could be deployed together.
Tuc directed ACV to review all remaining work on the third component and set clear dates for completing construction, installing equipment, finishing test runs and trial operations, and bringing the project into service.
Since the project cannot be completed in 2026 as approved by the National Assembly, ACV must report to the government and submit its report to the Ministry of Construction within one week starting Wednesday.
Before Dec. 10, the ministry must report to the government on the project’s progress so the relevant authorities can consider and decide whether to amend the investment policy.
ACV must require contractors to mobilize all available workers, machinery, equipment and financial resources, increase overtime and add shifts to speed up construction and disbursements.
"Take firm action against contractors that fail to meet their contractual obligations or report them to the relevant authorities for action," Tuc said.
He stressed that safety and convenience for users are top priorities for an international airport. The airport may open only when it meets all requirements and can operate safely.
ACV must also specify when it will announce the start of operations. Once it receives official notice from the relevant authorities, it must inform airlines so they can prepare their resources, draw up operating plans and schedule flights.
Long Thanh International Airport is being built on about 5,000 hectares in Dong Nai, 40 km east of Tan Son Nhat International Airport in Ho Chi Minh City. The nearly US$16 billion project will be developed in three phases. The first is designed to handle 25 million passengers and 1.2 million tonnes of cargo a year.