ESPN DeportesLa "Fe" de Dave Roberts en sus estrellas lo tiene esperando un milagro para los DodgersInquirerNortheasterly winds, ITCZ to bring rains in PH on FridayDaily MaverickEXTREME WEATHER : Agriculture Minister sounds ‘super El Niño’ warning bell and calls for water restrictionsESPNWhat would a 24-team College Football Playoff bracket look like?RTP DesportoSporting assegura Ronda Principal, FC Porto afastado da `Champions` de andebolThe Jerusalem PostUS midterms could reshape support for Israel as anti-Israel sentiment grows among votersZDF heuteEntdecken Sie das ZDF-NachrichtenstudioThe South AfricanSt. Anne’s Diocesan College’s matric learner takes life before examsColliderAll 5 Zombie Movies of 2026, RankedBillboard‘BTS Recipe Book Volume 2’: K-Pop Superstars Break Down Even More of Their Favorite Korean DishesGlobal NewsFact Check: Elections Alberta restricts referendum scrutineers due to limited spaceMintTrump claims Iran's first- and second-string leaders are gone, questions who US is negotiating with
The Daily Newsstand · Free, Always
Thursday, October 15, 2026

Builder revealed, but cost of new stadium still 'being worked through'

Translate

The head of the government body tasked with delivering a new stadium in Hobart has acknowledged that "cost pressures" could impact the final price tag of the project.

The construction of a 23,000-seat, roofed stadium is a key requirement for the entry of the Tasmania Devils into the AFL and AFLW competitions in 2028.

The project is currently budgeted at $1.13 billion, but that estimate is now more than a year old.

Since then, construction costs have increased significantly because of the war in the Middle East.

Macquarie Point Development Corporation chief executive Anne Beach said further work would now be done to finalise the cost before the contract is signed by the end of the year.

"Through this next stage an important part of that is moving from the target construction sum to actually locking down the lump sum that will go into the contract," Ms Beach said.

"The stage two process will end in around mid-November.

"We'll then go through an assessment, and that's when we'll be coming back to government to discuss that cost."

On Thursday, BESIX Watpac was announced as the preferred builder of the stadium.

Ms Beach said "cost pressures" would play a part in the outcome.

"We'll need to consider, as we go through this process, cost pressures that are in the market and the cost to build as at today.

"We'll be continuing to analyse that, and we'll provide an update once we can after stage two."

A group of smiling people standing around in high vis in front of an empty dirt lot which is being prepared to become stadium

At a press conference, Jeremy Rockliff did not take up the chance to promise Tasmania's input to the stadium would be limited to $875 million. (ABC News: Kate Nickels)

Premier Jeremy Rockliff said the final cost would be publicly revealed shortly before the contract is signed.

But when asked whether he could promise the state's input would be limited to $875 million, as previously flagged, he repeatedly skirted the question.

"We're working through a very rigorous process," Mr Rockliff said.

"We're at stage one, and we're working through and continuing that to get to stage two and, of course, signing the contract.

"And I'm not going to detail costs — they are being, they continue to be, worked through."

Exposed historical train turntable being dug up by yellow diggers, fluoro orange flags and workers in high vis stand around

Work is being done at the Macquarie Point site in preparation for the stadium construction. (ABC News: Kate Nickels)

Cost will be 'quite north' of $1.13b, MLC says

The state government's $875 million funding cap was part of its agreement with independent MLC Bec Thomas, who voted in favour of the development in December last year.

As part of that agreement, any further funds required to build the stadium would either be clawed back via "value management", a reduction in scope, or be sought from either the federal government, AFL or Cricket Australia.

The Greens remain sceptical the stadium can be built within the current funding envelope.

"We don't trust the premier and his commitment to stick to $875 million," Greens MP Vica Bayley said.

"That's why it's incumbent upon him to be transparent about where the additional money is going to come from and how parliament is going to be involved."

Greens Member for Clarke Vica Bayley 2024-05-24 10:05:00

Vica Bayley says the state government needs to be transparent about where extra funds could come from. (ABC News: Owain Stia James)

Independent MLC Meg Webb said it would be "naïve" to think the cost of building the stadium won't be more than envisaged last year.

"I think all of us can look at the world's events since then, can look at other costs that have clearly gone up and imagine that now we're looking at a full cost for this stadium that's somewhere quite north of $1.13 billion."

She urged the government to disclose the cost to parliament before the contract is signed.

"We know that Tasmanians would like there to be transparency around that cost and now that a builder has been announced, there's no reason for the state government not to come clean and be really open and transparent and give us the expected full cost of the stadium."

A lady with dark hair, blazer and glasses, sitting in a dark room, smiling at the camera.

Meg Webb says it's clear the full cost of the stadium will be far more than the current $1.13 billion figure. (ABC News: Maren Preuss)

Expert says Middle East conflict likely 'having impacts'

Kirr Parr is a construction industry advocate and senior fellow at the University of Melbourne Law School who lectures in the delivery of major projects.

She said it was common for large-scale construction projects to go over budget because of external factors and long timeframes that can significantly affect costs.

"An external war that drives up prices that's happened since you did your budget won't have been factored into that original budget," Ms Parr said.

"So, it's exactly the kind of external factor that major projects are exposed to and it likely is having impacts on the budget.

"The exact nature of how it all plays out over the next three or four years is unknown."

Interior playing surface and roof structure of stadium.

BESIX Watpac built Christchurch's new 30,000-seat stadium at a cost of just over $530 million. (Supplied: One New Zealand)

Ms Parr saidthe key was to limit the scale of any potential cost overruns through good management.

"It's the importance of working very, very hard on your projects to resolve problems as early as possible and not allowing them to escalate," she said.

"The importance of experts, people who have experience on major projects."

View the original on ABC News (Australia) →