PunchEx-Liverpool defender reveals secret battle with seizuresDaily MaverickWorld Cities Day — Holding the line on eviction protections for the vulnerableThe Jerusalem PostFormer IDF chief Halevi says Oct. 7 was 'preventable,' but was not 'betrayal from within'한겨레격전지 미시간서 민주당 의원 공화당 상원 후보 지지…선거판 ‘발칵’ColliderCillian Murphy’s ‘John Wick’ Rival Officially Finds a New Streaming Home3DNewsНовая статья: Обзор ASUS ROG Strix SCAR 18 G835 (2026): этот ноутбук быстрее 99 % десктоповZDF heuteEntdecken Sie das ZDF-NachrichtenstudioCBS NewsJudge tosses lawsuit seeking to delay certification of Alaska Senate raceХабрDirect 2D #15.2 Пользовательский эффект. Пиксельный шейдер. HLSLTechCrunchAI can make tech CEOs’ lives easier. What about everyone else?Football ItaliaPicture: Furious Inter ultras slam players after derby defeatANSAIsraele, Eisenkot cerca alleati, guarda agli arabi di Ra'am e agli ultraortodossi
The Daily Newsstand · Free, Always
Sunday, November 1, 2026

Judge says xAI must face NAACP lawsuit on data center pollution

Translate

The legal battle revolves around the AI company’s operations in southern Memphis.

An aerial view of xAI's data center campus near Memphis.

harhar38/Shutterstock

A federal judge's latest ruling has denied xAI's request to dismiss a lawsuit that alleges its data center campus in Memphis, Tennessee is running turbines without proper permits and violating the Clean Air Act. The decision, from US District Judge Debra M. Brown, allows the lawsuit, which was filed by the NAACP, to move forward.

The organization filed its legal action against xAI in April, accusing the company that's now known as SpaceXSI of using unpermitted methane gas turbines to power data centers in the Memphis area. Despite the ongoing lawsuit that also claimed it's violating the Clear Air Act, Elon Musk's company continued to add more gas turbines to another AI data center site in the nearby Southhaven, Mississippi community. In response, xAI requested to dismiss the NAACP lawsuit and even received support from the Justice Department, which claimed that the company's operations are a crucial part of US military operations.

xAI said the lawsuit should be dismissed, claiming that its turbines were exempt from permitting requirements since they were mobile. Judge Brown wrote in her decision that the power plant where all the turbines were providing power to xAI's data center wasn't mobile and therefore not exempt from the permitting process. The lawsuit comes at a time when AI companies are ramping up the construction of data centers to fuel their AI needs, while neighbors are becoming increasingly averse to these buildouts.