ESPN DeportesPachuca y Atlante femenil despiden a sus DTInquirerDefense, prosecution to present oral arguments on voting thresholdDaily MaverickGOING FOR A SONG OP-ED: AI and the future of creativity — can artists’ histories travel with their work?The Jerusalem PostErdogan calls Gaza suffering 'most embarrassing concentration camp' in UNGA speechPunchAnambra flood: Pupil missing as police rescue nine한겨레2연패 도전 여자 배드민턴, 안세영 승리에도 일본에 막혀 단체전 ‘동’SözcüTrafikte görünen H işaretli trafik levhası kafa karıştırıyor: Çoğu sürücü anlamını bilmiyorCNN TürkMenderes Belediyesi'ne ikinci dalga operasyon: 9 gözaltı경향신문용수 상수도 활용·전력망 지중화··· “호남 반도체 팹 2기 2028년 착공 목표”Het Laatste NieuwsDroomtransfer met een valse start: waarom de interlandbreak op het ideale moment komt voor Nathan De CatDaily MailAndy Burnham wobbles on Chagos as Trump hits out at 'terrible and ridiculous deal' during their first-ever meetingSportstarAsian Games 2026 Day 5, Live Updates: India wins bronze medals in skeet shooting; Mirabai Chanu confirms weightlifting medal; India takes on China in men's badminton
The Daily Newsstand · Free, Always
Wednesday, September 23, 2026

Marcos marks Quezon Avenue tunnel breakthrough for Metro Manila subway

Translate
President Ferdinand Marcos Jr. and Transportation Secretary Giovanni Lopez inspect the Metro Manila Subway Project’s Quezon Avenue Station in Quezon City on Sept. 23, 2026, following the successful excavation of a 1.12-kilometer southbound tunnel from North Avenue to Quezon Avenue using a tunnel boring machine.
President Ferdinand Marcos Jr. and Transportation Secretary Giovanni Lopez inspect the Metro Manila Subway Project’s Quezon Avenue Station in Quezon City on Sept. 23, 2026, following the successful excavation of a 1.12-kilometer southbound tunnel from North Avenue to Quezon Avenue using a tunnel boring machine. —PHOTO FROM PCO

MANILA, Philippines — President Ferdinand Marcos Jr. has called the breakthrough of a tunnel boring machine at the Quezon Avenue station in Quezon City as an important milestone in the construction of the Metro Manila Subway Project (MMSP).

During his inspection on Wednesday, Marcos said the tunnel boring machine has completed excavation of the section from the southbound portion of North Avenue station to Quezon Avenue station, covering about 1.1 kilometers at a depth of 34 meters below ground.

Tunnel boring operations are continuing from Quezon Avenue station toward East Avenue station, spanning 1.5 km.

Article continues after this advertisement

“Little by little, we can see that our subway project is gradually taking shape. We can see it coming together,” he told reporters.

FEATURED STORIES

NEWSINFO

NEWSINFO

NEWSINFO

“Once this is completed, the people living here will be very fortunate because they will have a subway; they will have the MRT (Metro Rail Transit). They will have many ways to get around the metro,” Marcos said.

The two underground stations and their connecting tunnels are part of MMSP’s Contract Package 102 (CP102), awarded to the joint venture of Japanese firm Nishimatsu Construction Co. Ltd. and local construction company D.M. Consunji Inc. (DMCI) in 2022.

READ: Marcos: Work progress on Metro Manila subway at 60%

The original contract cost was P21.203 billion. A supplemental agreement worth P4.336 billion brought the total contract amount to P25.539 billion, exclusive of value-added tax.

Article continues after this advertisement

Construction works of the Quezon Avenue and East Avenue stations of the MMSP began on May 10, 2023.

President Marcos last week led the groundbreaking ceremony of the MMSP’s Ninoy Aquino International Airport (Naia) Terminal 3 station in Pasay City, where he touted the subway project to be 60 percent completed.

Article continues after this advertisement

The P488.48-billion MMSP, financed through loans from the Japan International Cooperation Agency (Jica), is part of ongoing efforts to modernize the country’s railway system, improve connectivity across Metro Manila, and cut travel time for commuters.

READ: JV Ejercito: No more delays in NSCR, Metro Manila subway

The government aims to complete the construction of the 33-kilometer, 17-station underground railway system by the last quarter of 2031.

It will stretch from East Valenzuela to Bicutan in Taguig, providing a faster and more reliable mass transportation option across the capital region.

Once fully operational, the subway is expected to cut travel time from Valenzuela City to Naia from about 1.5 hours to 41 minutes.

However, Transportation Secretary Giovanni Lopez said full operations are slated for early 2032, pending the necessary testing and commissioning requirements.

Your subscription could not be saved. Please try again.

Your subscription has been successful.

The MMSP was initially expected to be completed in 2027, but was reset to 2029, and then 2032 due to right-of-way issues. /jpv