Trial run begins: Bengaluru Metro’s KR Puram to Silk Board stretch to start next year

Greater Bengaluru Development Minister Krishna Byre Gowda (grey shirt) inspects Namma Metro works with BMRCL officials on Tuesday. (Photo: Special arrangement)
AI Narration
Listen
00:00
Trial runs on a section of Bengaluru’s long-awaited Blue Line Metro began Tuesday, with Greater Bengaluru Development Minister Krishna Byre Gowda saying the 19.75-km KR Puram-Central Silk Board corridor would be operational by mid-2027.
The trial run commenced on the Phase 2A section from KR Puram towards Mahadevapura, covering the first four stations. Testing will continue through this month and is expected to extend to four more stations in the coming weeks, Gowda said after inspecting the project.
The KR Puram-Central Silk Board stretch runs along the congested Outer Ring Road (ORR) corridor, which is home to several IT companies. According to officials, 37.1 km of tracks have been laid out of the total 39.2 km. Gowda said that system installations and testing preparations are progressing.
85% of station entry and exit work done
The Phase 2A corridor from KR Puram to Central Silk Board comprises 13 stations. With an estimated 11-12 lakh people working along this stretch, the corridor is vital not only for the daily commute of thousands of employees but also for Bengaluru’s economy, Gowda said.
The minister added that the automatic signalling system, the main pending component, is expected to be installed within the next two to three months. This will be followed by the mandatory safety certification process. The government is aiming to complete signalling installation by January and begin safety certification after February.
The Bangalore Metro Rail Corporation Limited (BMRCL) said 85 per cent of station entry and exit works and 68 per cent of roofing works have been completed. Piling, pier construction, U-girder casting and erection works have been fully completed.
Airport line to be completed by 2028
Gowda said the government has directed officials to speed up work on the Phase 2B section, particularly the KR Puram-Hebbal stretch, where construction needs to accelerate. Officials have been instructed to coordinate closely with contractors and expedite execution.
Story continues below this ad
The Blue Line project, spanning 58.2 km from Central Silk Board through KR Puram and Hebbal to Kempegowda International Airport, is being built at an estimated cost of around Rs 20,000 crore. The government aims to complete the entire corridor, including the airport link, by 2028.
KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.