InquirerMayon evacuees reel from water shortage in Tabaco CityDaily MaverickINSOLVENCY & LIQUIDATION : Business rescue — lifeline or delay tactic for struggling companies?PunchN10bn intervention not for Ebola alone, says NCDC bossThe Jerusalem PostIsrael to file UEFA complaint against Ireland over coach's 'genocide' remarksZDF heuteAktuelle Pressemitteilungen des ZDFThe Sydney Morning HeraldRBA lifts interest rates for fifth time this yearSözcüBu şehirde 50 bin kişi üst üste yaşıyor! Güneşi gören şanslı sayılıyorNew Straits TimesMelaka polls: BN to unveil manifesto this FridayAntara NewsIndonesian lawmaker calls for forest restoration in fire crackdownBBC عربيأنباء عن قصف الولايات المتحدة لجزيرة قشم الإيرانية، وترامب يقول إنه قد يُستهدف موقع بيك آكس النووي경향신문내년부터 ‘50세 이상 재취업 지원’ 500인 이상 사업장까지 의무화Daily MailTrump launches attack on Iran on eve of midterm elections... as it's revealed US has been secretly striking regime for weeks
The Daily Newsstand · Free, Always
Tuesday, November 3, 2026

南科擴張帶動通勤需求!台南捷運深綠線現勘完成、橘線11月再闖關

Translate

根據「電腦網路內容分級處理辦法」修正條文第六條第三款規定,已於網站首頁或各該限制級網頁,依台灣網站分級推廣基金會規定作標示。 台灣網站分級推廣基金會(TICRF)網站:http://www.ticrf.org.tw

台南捷運深綠線可行性研究規劃示意圖。(交通局提供)

南科快速發展,台南捷運路網也加緊布局!為串聯沙崙與南科兩大科技產業聚落,市府積極爭取捷運深綠線可行性研究加速審議,並推動橘線(佳里、善化段)規劃經費早日核定。其中,深綠線已於8月完成鐵道局現勘,橘線可行性研究案預計11月修正後重新提報交通部審查,盼加速台南軌道建設進程。

隨著南科快速擴張,就業人口及區域交通需求持續增加,市府規劃透過捷運路網串聯科技產業聚落,打造便捷通勤廊帶。其中,深綠線將銜接第1期藍線延伸線,往北延伸至南科及善化,串聯沙崙與南科兩大產業發展引擎;橘線(佳里、善化段)則因應佳里、麻豆往返南科的交通需求,路線自佳里向東經麻豆至善化,並銜接台鐵善化車站及捷運深綠線。

交通局長王銘德表示,深綠線規劃採高架單軌系統,全長約21.3公里,設置14座車站及1座維修機廠,已於今年5月完成可行性研究報告修正並提送交通部續審,8月由鐵道局完成現勘;橘線全長初估18.7公里,可行性研究申請案今年8月提報交通部審查,期間多次與鐵道局協調補助方式,預計11月完成修正後重新提報。

交通局指出,捷運建設攸關台南長遠發展,市府將參考立法院財政委員會考察意見,持續與中央溝通,爭取計畫所需資源,加速審議及後續作業,逐步完善軌道運輸路網,提升區域交通便利性及城市競爭力。

View the original on 自由時報 →