CNN TürkPolise çakal dedi, Yargıtay hakaret saydıPunchCampaign kickoff: ADC keeps venue secret after rift with Sokoto govtInquirerPRO-12 campaign vs loose firearms nets 8 persons, 116 gunsZDF heuteAktuelle Pressemitteilungen des ZDFThe Jerusalem PostChallenges to US-Israel alliance grow as anti-Israel voices gain in MAGA movement, expert warnsCBS NewsSenate election results as first polls begin to closeABC NewsTAKEOVER - LINK - 2024 ELEX MAPynetהקלפיות נסגרות: החלה ספירת הקולות בבחירות האמצע בארה"ב | עדכון חיThe Sydney Morning HeraldHere’s where all the key midterm races standAnadolu AjansıABD Başkanı Trump, İran'a saldırmak için "acil bir planının" olmadığını belirttiDaily MailFirst midterm polls close as Trump awaits America's verdict after a day of voting chaos, with exit polls flashing a dire warning for Republicans: Live updatesBBC 中文2026年美國中期選舉實時更新結果
The Daily Newsstand · Free, Always
Wednesday, November 4, 2026

Data centers are turning to old jet engines as the wait for power grows

Translate

Stuck in years-long lines for grid connections and new turbines, some AI data centers are making their own electricity with converted jet engines, the New York Times reported Tuesday.

The engines, pulled from retired aircraft and rebuilt to burn natural gas, aren’t anyone’s idea of a permanent power plant. But they’re another sign of how far power supply has fallen behind the AI buildout.

For companies stuck in those lines, the main draw of converted jet engines is how quickly the engines can be up and running. “It’s all about getting power as fast as possible,” Rystad Energy analyst Audun Martinsen told the Times. With jet-powered units, “they can have a data center running in 24 months,” he said.

Hooking up 100 megawatts to the grid in Northern Virginia, by comparison, takes about seven years, according to the International Energy Agency. Most power capacity is expected to come on by 2031, an executive at Mitsubishi Power, one of the world’s top makers of power generation equipment told Bloomberg last week.

In some cases, these delays are already costing some data center operators business. Last month, Microsoft pulled out as the anchor customer for Nscale’s data center in Loughton, England, after the local utility said it couldn’t deliver enough power until the early-to-mid 2030s.

Elon Musk’s xAI is among the companies already using the engines, having installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center in Memphis, the Times reported, citing state permits and satellite imagery. The units come from ProEnergy, which rebuilds a GE engine commonly found on Boeing jets. 

In 2025, OpenAI followed Musk’s lead with gas turbines at its first Stargate site in Abilene, Texas. Crusoe, a Denver-based startup that builds AI data centers, is constructing that Abilene campus and ordered 13 of ProEnergy’s converted units in April. 

In September, Crusoe walked away from a $1.25 billion deal to buy 29 natural gas turbines from Boom Supersonic, a startup developing a supersonic passenger jet that has also begun selling a version of that jet’s engine as a power plant for data centers. A Crusoe spokesperson told TechCrunch at the time that the company still plans to use turbines. 

Currently the Trump administration is adding to the pressure by encouraging data centers to generate their own electricity.

Converted jet engines come with trade-offs, though: They’re less efficient and pollute more than turbines designed for conventional gas plants and it takes more of them to make the same amount of power, according to the Times. That may ultimately make converted jet engines a short-term play with some experts saying that efficiency and environmental concerns may grow in importance in a year or two.

When you purchase through links in our articles, we may earn a small commission. This doesn’t affect our editorial independence.

Aditya Mehta is a reporter at TechCrunch covering AI. He’s supported by the Tarbell Center for AI Journalism and attended UC Berkeley. You can contact from Aditya by emailing [email protected] or via encrypted message at adymehta.74 on Signal.