Daily MaverickIsraeli exit polls show deadlock, point to setback for NetanyahuESPN DeportesDoble-doble de KAT da a Knicks su primer triunfoPunchLagos Assembly okays state police, demands clear power-sharingESPNFantasy basketball H2H Category and Roto rankings: Daniels, Kessler move upThe Jerusalem Post'Eretz Nehederet' tackles Israel's election-night drama with Gal Gadot, political satireZDF heuteEntdecken Sie das ZDF-NachrichtenstudioХабрПроект «Фобос» последня экспедиция Советского Союза к МарсуNew Straits TimesSaifuddin: House arrest Bill for remand prisoners in final review stageBBC 中文姆巴佩就「中國獨裁者」迷因道歉:風波背後的資訊真空與「毛澤東熱」VarietyOscars Will ‘Always’ Reward Human Excellence in AI Era, Academy Chiefs Say as They Leave Door Open to International Feature Rule Tweaks (EXCLUSIVE)CBS News8-month Iran war looms large over Israeli electionSözcüSon dakika... İsrail'de seçim sandıkları kapandı
The Daily Newsstand · Free, Always
Wednesday, October 28, 2026

Councils struggle to access millions in flood recovery funding

Translate

The floodwaters have long receded from Central Australia's roads, but the path to repairing them remains tangled in paperwork.

Almost eight months after heavy rainfall damaged infrastructure and isolated remote communities, three councils say they have struggled to access government disaster recovery funding.

Barkly Regional Council Mayor Sid Vashist said about 70 per cent of council roads were impacted by flooding in February and March, but the council only submitted its first funding application earlier this month.

a smiling man with dark hair wearing a pink shirt

Sid Vashist says the council has been forced to cover recovery costs while awaiting millions of dollars in disaster funding. (ABC News: James Elton)

"Council has had to work through an extremely painful process, 79 pages worth of documentation and the red tape that was around that," he said.

The application, worth between $4.3 million and $4.7 million, covers more than 30 roads and 127 damaged sites across eight communities.

Mr Vashist said the cash-strapped council had paid up-front for engineers and consultants, with no time frame provided for a funding decision.

"We don't want to go into another wet season where no work has commenced," he said.

MacDonnell Regional Council chief executive Belinda Urquhart said her council had been unable to secure funding for damage caused by the same flooding.

Belinda Urquhart, with blonde hair and wearing a pink shirt, smiling. The photo is taken outside.

Belinda Urquhart says the application requirements are too difficult for remote councils. (Supplied: MacDonnell Regional Council)

"The complexities are insane."

Ms Urquhart said her council had attempted to access funding but found the application requirements "too difficult to meet for remote councils".

She said the arrangements also prevented the council from using recovery funding to build new bridges or causeways in flood-prone areas where none previously existed.

"It's an uneven playing field for remote councils," she said.

Alice Springs Town Council chief executive Peter Varris said he did not believe his council had received funding for earlier flood damage either.

Peter Varris ASTC

Peter Varris has suggested up-front disaster recovery funding. (Supplied: Alice Springs Town Council)

"The processes are clumsy. There's no doubt about that," he said.

Mr Varris suggested up-front payments to help councils engage contractors and begin recovery works while awaiting reimbursement.

A paper report with a blue cover.

This 73-page document is one of several outlining the requirements councils must meet to access disaster recovery funding. (ABC: Xavier Martin)

Federal minister acknowledges delays

Federal Emergency Management Minister Kristy McBain said the arrangements operated through a reimbursement system involving both levels of government, with councils submitting applications through the NT government.

She acknowledged the process was taking too long and said a national task force, including Barkly Regional Council and Katherine Town Council, was examining delays.

"I don't think it's good enough that it takes councils this long," she said.

Ms McBain also encouraged the NT government to review its own procedures.

Emergency Management Minister Kristy McBain in front of a government sign.

Kristy McBain says the disaster recovery funding system needs reform. (ABC News: Adam Kennedy)

"These processes sit with the Emergency Management Minister in the Territory and obviously we would love the Territory to take a look at what their processes are, like every state," she said.

The NT government confirmed Barkly's application remained under assessment, while Alice Springs Town Council's claims, submitted in June and updated in August, were also being assessed.

It said MacDonnell Regional Council had not submitted a claim, but reconstruction applications remained open until April.

A government spokesperson acknowledged national funding requirements were making it difficult for some councils to submit claims and said the Territory was working with the Commonwealth on reforms to simplify the process.

However, the spokesperson did not confirm whether the NT government would review its own procedures.

The spokesperson said councils were paid once claims were assessed as eligible, before the Territory sought reimbursement from the Commonwealth.

The concerns come as Central Australia recovers from another series of damaging storms this month, raising fears about infrastructure repairs before further severe weather.

View the original on ABC News (Australia) →