Bollywood HungamaChhaya Kadam wins Special Award at BRICS+ International Film Festival for Snow FlowerThe Jerusalem PostBritain sanctions Israeli settlement firms in push to protect two-state solutionInquirerEx-UPLB school paper editors condemn student journalists’ arrestSky TG24Gerico, coloni aprono il fuoco: un morto e diversi feritiSRF NewsKampf um Fifa-Präsidium – Das ist Infantino-Gegner Philippe DialloThe Hollywood ReporterFubo Widens Quarterly Loss on Higher Revenue, Gets to 5.75 Million North America SubscribersZDF heuteEntdecken Sie das ZDF-Nachrichtenstudioالشرقعقار جديد لعلاج سرطان الثدي ينال موافقة أميركية.. وتوقعات بمبيعات ملياريةAntara NewsRI pushes stronger ASEAN-India maritime cooperation, connectivityNHK 社会愛知 強盗殺人未遂事件 現場で「クマ撃退スプレー」見つかるGolem.deAnzeige: 27 Zoll großer OLED-Gaming-Monitor von AOC mit 260 Hz günstig wie nieNMEThe NHS wants ‘GTA 6’ players to protect their hands and fingers
The Daily Newsstand · Free, Always
Tuesday, November 17, 2026

PLN Indonesia Power starts construction of 4.5-MW solar plant in Bali

Translate
The project is expected to generate approximately 8.8 million kilowatt-hours (kWh) of electricity annually,

Jakarta (ANTARA) - PT PLN Indonesia Power has begun construction of a 4.5-megawatt (MW) hybrid solar power plant (PLTS) integrated with a 9-megawatt-hour (MWh) battery energy storage system (BESS) in Nusa Penida, Bali.

In a statement issued in Jakarta on Tuesday, PLN Indonesia Power President Director Bernadus Sudarmanta said the project was a strategic step toward optimizing solar energy use while supporting the development of a cleaner, more reliable, and sustainable electricity system.

The project is expected to generate approximately 8.8 million kilowatt-hours (kWh) of electricity annually, he added.

The hybrid solar power plant and BESS are being developed to expand the use of new and renewable energy (EBT) by integrating power generation and energy storage technologies.

The battery system is expected to improve the flexibility of solar energy management while strengthening electricity supply reliability for local communities and economic activities in Nusa Penida.

Sudarmanta said the project also responded to rising electricity demand in the area.

"Electricity demand in Nusa Penida continues to rise. In 2026, peak load reached 18 MW, up 12 percent from the previous year. This underscores the importance of developing power generation facilities that can optimize local energy potential," he said.

"By integrating a solar power plant with a Battery Energy Storage System (BESS), we aim to provide a more efficient alternative energy supply while improving the reliability of Nusa Penida's electricity system," he added.

The hybrid solar power plant will occupy an 8.2-hectare site and use 8,608 bifacial monocrystalline photovoltaic (PV) modules, each with a capacity of 720 watt-peak (Wp).

The facility will also be equipped with a 9 MWh BESS using lithium iron phosphate (LFP) battery technology to improve energy storage and management.

The solar power plant and BESS will be integrated through an Energy Management System (EMS) and a Supervisory Control and Data Acquisition (SCADA) system, enabling coordinated management of electricity generation and storage.

The systems are designed to improve operational flexibility by scheduling energy use, stabilizing the solar power plant's output, and supplying electricity during periods of high demand.

Construction of the hybrid solar power plant and BESS is scheduled to take 12 months, starting on June 6, 2026.

Through the project, PLN Indonesia Power aims to continue developing renewable energy-based power infrastructure that can adapt to the needs of the electricity system.

Related news: From Bali, Indonesia embarks on a 100-GWp solar journey

Translator: Cindy Frishanti Octavia
Editor: M Razi Rahman
Copyright © ANTARA 2026

View the original on Antara News →

KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.