InquirerSocratic method vs core skills? CJ contenders weigh bar exam reformsESPNEx-NBA player Beasley agrees to plead guilty in federal sports betting caseESPN Deportes¿Cómo regresa Tampa Bay de una desventaja de tres juegos?The Jerusalem PostArab parties Ra'am, Joint List soar to 17-18 seats amid high turnout, election exit polls showDaily MaverickThere is another Afrikaner story worth telling, rooted in reconciliation and a shared futureSCMP ChinaFor its autocratic African ally, Taiwan bites its tongue and opens its walletRai NewsSerie A, Roma-Cagliari 4-2 all' 87' e Torino-Como 1-0 dopo 45'ZDF heuteEntdecken Sie das ZDF-NachrichtenstudioEngadgetiPhone 18e reportedly comes with 2nm A20 chip and 60Hz screenANSASerie A: in campo Roma-Cagliari 2-2 e Torino-Como 1-0 DIRETTAABC News (Australia)Teen charged over Sydney house fire with 88yo woman insidePremium TimesNCGC guarantees N64.13bn loans to businesses, individuals
The Daily Newsstand · Free, Always
Tuesday, October 27, 2026

GROUNDUP : Judge tells parties in Lesotho water project battle to settle out of court

Translate

The Lesotho High Court has told the Lesotho Highlands Development Authority (LHDA) and the trust representing communities affected by the Lesotho Highlands Water Project to come to an agreement out of court.

The Seinoli Trust had approached the court seeking to overturn a refusal by the LHDA to share data needed to determine whether communities near the project had been left worse off by it.

Seinoli argued that the data is critical to determining whether the families have been adequately compensated under the treaty signed by Lesotho and South Africa.

On Tuesday, Judge Molefi Makara gave the two parties until 17 November to complete out-of-court negotiations on the handover of the information.

In her founding affidavit to the court, Reitumetse Nkoti-Mabula, executive director of Seinoli’s operations arm, the Seinoli Legal Centre, said the organisation wrote to the LHDA on 28 March 2023 requesting the information within 14 working days. When the LHDA failed to furnish the information, Seinoli wrote another letter on 26 April 2023.

The LHDA only responded on 22 June 2023, saying that the information was the intellectual property of LHDA and could not be shared with any third parties. LHDA chief executive Tente Tente said releasing the information would also violate data protection laws.

Nkoti-Mabula said the refusal made it impossible to evaluate whether the LHDA had met its obligations to the communities affected by the water project.

She said the requested information included completed census and socioeconomic survey data about everyone affected by the project, as well as land and asset inventories, maps and photographs identifying the location and size of agricultural land. It also included information on improvements such as houses, livestock, rangelands, fruit trees, medicinal plants and graves.

Seinoli also wanted the LHDA to disclose valuation amounts, compensation offers, signed agreements, grievance documents and an overview of cash and in-kind compensation paid to those affected.

Battle heads to court

Nkoti-Mabula said the organisation wanted the court to declare the LHDA’s refusal to share the information unlawful and illegal. The LHDA had violated its own policies and legal commitments, she said. In its environmental policy dated May 2016, the LHDA had undertaken to “regularly provide to stakeholders, accurate environmental information and reports based on the outcome of monitoring and evaluation activities”.

The refusal also violated Seinoli’s right to access information under Lesotho’s constitution and the Environmental Act, Nkoti-Mabula said.

Tente denied that the refusal was unlawful, saying the LHDA’s decision complied with the Data Protection Act of 2011, which prohibits the release of beneficiaries’ private information without their authorisation. “The fact that [Seinoli] is a public interest law centre does not grant it a blank cheque to receive personal and private information without the consent of the affected third parties,” Tente said.

Nkoti-Mabula said Seinoli had consulted individuals, households and communities affected by Phase 1A of the water project, covering the Katse Dam and Muela Reservoir. During these consultations, in 2021 and 2022, some people had complained that they had not received full compensation for losses suffered because of the project.

“About 100 individuals, households and communities complained that life has become more difficult for them ever since the project,” she said, adding that the communities had requested Seinoli’s intervention. She cited an ombudsman report, stating that, as of 31 December 2025, arrears in compensation for Phase 1 stood at more than M142-million (R142-million).

Why this data matters

According to Nkoti-Mabula, access to this data would enable Seinoli to compare the circumstances of affected households and communities before and after the project, and assess whether the LHDA had met its obligations.

“In the view of the Seinoli Legal Centre, the failures of the LHDA in discharging its domestic and international obligations as a local instrument implementing the Lesotho Highlands Water Project, deleteriously impacted on the protected rights and interests of the vulnerable affected communities,” she said.

But Tente said that the socioeconomic data requested by Seinoli had not been available at the time because the LHDA had still been undertaking the survey. He said failure to provide information that was still being collected could not be considered a breach of its policy.

After Tuesday’s ruling, Seinoli’s advocate, Relebohile Thuhlo, said the organisation would send a letter to the LHDA listing all the information required. DM

View the original on Daily Maverick →