וואלהשני מחבלים שקידמו מתווי טרור נעצרו בכפר קבאטיהDaily MaverickFUTURE INVESTMENT: Thrive by Five uses data to drive smarter investment in early childhoodESPN Deportes¿Quién es Joshua Báez? El dominicano del histórico debut de 3 jonronesESPNWhich NFL teams are in the best shape for the next three seasons? 1-32 projections for 2027-29The Jerusalem PostHealth Min. reviews possible sperm donor genetic mismatch at Assuta Medical Center, Tel AvivRolling StoneTaylor Swift Can’t Stop Listening to Phoebe Bridgers’ New AlbumColliderAll 7 X-Men Actors Announced at D23kickerAwoniyi verstärkt PL-Aufsteiger - Milosevic vor VfB-AbgangLa PresseAffaire d’espionnage à l’OTAN | Des auditions sur le processus de contrôle de sécurité auront lieuThe Hollywood Reporter‘60 Minutes’ Adds The New Yorker’s Ariel Levy as CBS Series Keeps Staffing UpХабрТочка GANSAPressing degli Usa sul piano Gaza, Trump: 'Basta raid sulla Striscia'
The Daily Newsstand · Free, Always
Monday, August 17, 2026

The Sydney sports oval costing council $60,000 a month to sit empty

Translate

A northern Sydney football oval that has been closed for three years and had eight cost blowouts is costing ratepayers $60,000 a month to sit unused as councillors await a report that could mean the synthetic sports field redevelopment will go back to square one.

Ku-ring-gai Council promised residents in early 2023 that replacing grass at Norman Griffiths Oval in West Pymble with an all-weather sporting field would take a few months and cost $3 million. More than three years later, the estimated redevelopment cost has ballooned sixfold to $20.2 million, and a council spokesperson confirmed it no longer had a completion date of May 2027.

Norman Griffiths Oval in 2021 and 2026.Sam Mooy/Oscar Colman

Managing the oval has cost the council about $60,000 a month in April, May and June. Costs include hiring site fencing, paying for the CCTV, “dewatering”, and other labour costs. The cost of removing surface water from May to July was $129,000.

It comes after councillors in May voted to hit pause on the project and wait for a $70,000 report from the independent state government public works authority, comparing costs to install a natural grass field or a synthetic turf surface. It was also decided that the council would conduct a representative, not opt-in, resident survey before committing to further costs.

At an extraordinary meeting in May, councillor Indu Balachandran said: “I recognise and I understand that there is a cost to that. But I think good democratic processes have to be strategic.”

Players from West Pymble Football Club have been locked out for years.Sitthixay Ditthavong

At another extraordinary meeting, on July 29, three councillors – Martin Smith, Jeff Pettett and Sam Ngai – put up a rescission motion to reverse decisions made at the May meeting.

Ngai said his main concern was the “higher than expected” costs of the oval sitting idle, but there was also the flow-on impact any delays would have on construction costs.

“The public works report is late by a month, so that pushes the timeline out, and we won’t be deciding on the project until November … There’s going to be cost escalations from inflation and construction in the half a year or so since May,” Ngai said.

The motion attempted to speed up delivery of a synthetic turf before advice from the state government authority was completed and provided to councillors.

The oval, originally budgeted at $3 million and scheduled to reopen in November 2023, is now more than three years late and will cost more than $20 million.Oscar Colman

“The community doesn’t need this to be slowed down any more,” Smith said.

“It needs the council to act. It needs it to progress forward. We’ve got safeguard measures in place. We know what the costs are.”

The motion to overturn May’s decision was lost after Mayor Christine Kay used her casting vote and the original motion was upheld.

Kay said the community deserved a decision “based on complete information, independent advice and a clear understanding of the costs, not a decision made just before the information becomes available”.

Pettett decided to vote against his own rescission motion. Ngai said this confused him, and the trio would not have called the meeting if they knew the outcome was the status quo.

“It was just a waste of our time,” he said.

Start the day with a summary of the day’s most important and interesting stories, analysis and insights. Sign up for our Morning Edition newsletter.

Cindy YinCindy Yin is an urban affairs reporter at The Sydney Morning Herald.Connect via email.

View the original on The Sydney Morning Herald

KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.