PunchPower crisis: 11 firms spend N842bn on energySözcüYılmaz, Şimşek ve Gürlek'den fon soruşturması toplantısı: Yer ve saati belli olduCBS NewsMaps show where Thanksgiving storms could disrupt holidayعالم التقنيةهواوي تحقق نحو 800 مليون دولار من ترخيص براءات الاختراع في 2025Lenta.ruЗахарова высказалась о приоритетах ЕвросоюзаThe Sydney Morning HeraldWarner directs latest barbs at Gerard Whateley in sandpaper sagaEl ComercioTemblor en Chile hoy, miércoles 25 de noviembre: reporte de magnitud y epicentro según CSNNew Straits TimesSelangor sees rise in flood evacuees as Perak numbers dipABC News (Australia)Australia's largest proposed vegetation-fuelled power plant rejected againDaily MailMinisters vow to create new standalone offence of stalking which could see offenders jailed for up to ten yearsLa PresseItinérance | Chute du nombre de tentes au campement Notre-DameObservador DesportoAs notícias das 3h
The Daily Newsstand · Free, Always
Thursday, November 26, 2026

울산 트램 ‘차량기지 터’ 옮긴다…사업비는 10억 올라

Translate
울산 도시철도 1호선 수소열차 모형. 울산시 제공
울산 도시철도 1호선 수소열차 모형. 울산시 제공

광고

울산시가 도시철도(트램) 1호선 차량기지를 남구 옥동 울산과학관 남쪽 터로 옮긴다고 26일 밝혔다.

울산시는 애초 계획한 태화강역 광장 2만3595㎡에 현실적으로 차량기지를 짓기 어렵다고 판단했다. 평균 24m 깊이의 약한 지반을 바꾸고 지하에 묻힌 고압가스관 등 시설물을 옮기는 데만 2년씩, 공사를 포함하면 최소 6년이 걸린다는 이유다. 사업비도 300여억원이 더 늘어날 것으로 예상한다.

울산시는 남구 옥동 울산과학관 남쪽 2만98㎡를 대체 부지로 정했다. 이곳은 암반 지반으로 별도 개량이 필요 없고, 용지 보상과 공사를 포함해 2년3개월이면 차량기지를 건설할 수 있다고 봤다. 도심과 떨어져 있어 도시 미관 훼손을 최소화할 수 있다는 점도 고려했다고 밝혔다.

광고

울산시는 설계와 각종 영향평가, 관계기관 협의 등 행정 절차를 반여해 사업 기간을 2030년으로 2년 연장하기로 했다. 노선은 시·종점부를 조정해 기존 10.850㎞에서 10.758㎞로 92m 줄어든다. 정거장 15곳은 유지한다.

총 사업비는 10억3300만원 늘어난 3824억7300만원으로 예상된다.

광고

광고

울산시는 공사 과정에서 시민 불편을 줄이기 위해 삼산로는 편도 3차로, 문수로와 대학로는 편도 2차로 이상을 확보하고, 구간별로 나눠 공사하거나 야간 작업을 할 계획이다.

울산시는 달라진 사업 내용에 대해 전문가와 시민 의견을 듣는 공청회를 27일 오후 3시30분 울산시의회 1층 시민홀에서 연다.