Maysan Road in Valenzuela City now pothole-free after rehab

+
Make this your preferred source to get more updates from this publisher on Google.
The pothole-ridden Maysan Road in Valenzuela City is now smooth after undergoing a year-long rehabilitation by the Department of Public Works and Highways (DPWH) and the city government.
DPWH Secretary Giovanni "Banoy" Lopez inspected Maysan Road on Tuesday morning as the road was opened to all types of vehicles, according to a report by EJ Gomez on Unang Balita.
The rehabilitation started on August 19, 2025 after motorists and residents complained about the condition of the road.
Maysan Road, which links MacArthur Highway to the North Luzon Expressway (NLEX) Karuhatan Exit, is where heavy container trucks pass to deliver goods to factories and warehouses. This contributed to the damage on the road.
A total of P76.9 million was allotted for the rehabilitation of the 1.5-km Maysan Road and the repair of the drainage system in the area.
During the rehabilitation, a strict 16-hour daily truck ban was implemented.
"Itong kalasadang ito, sabi nga nila, parang nasa buwan ka. Butas-butas, uka-uka, at parang sungka. Ang hirap po dumaan dito for the past five years," Lopez said.
(Passing this road, they say, is like you being on the moon. There are many potholes, it's like a "sungka" tray. It was so hard to pass this road for the past five years.)
"Then we started fixing this August of 2026. Last October, noong huling binisita ni Secretary Vince (Dizon, then DPWH secretary), 35% ang work accomplishment here. Ngayon, ang road component (accomplishment) nito is already 98%," he said.
(Last October, when Secretary Vince visited, the work accomplishment was at 35%. Now the road component [accomplishment] is already 98%.)
"Tapos 'yung drainage niya, 'yun na lang ang aayusin. The overall progress is 80%," Lopez said.
(The drainage will still be fixed.)
"It's a 30cm thickness. So makapal talaga du'n (it's really thick)," he added, speaking of the road quality.
Lopez said the warranty of the materials used for the rehabilitation is around five years, which is standard.
For the road component, the portions still to be done are the stretch of Maysan Road to T. Santiago at 58 meters, and Maysan Road to Paso de Blas at 40 meters.
DPWH is expecting the entire road rehabilitation to be finished next week. —KG, GMA News