The Jerusalem PostIRGC labels Trump 'big liar,' says US must admit failure in campaign against IranPunchZuckerberg, Pichai, others to meet Trump as AI safety pressure buildsRTP DesportoJaime Faria falha acesso ao quadro principal do torneio de TóquioBollywood HungamaEXCLUSIVE: Karan Tacker to return as Gaurav Tiwari? Bhay Season 2 likely to go on floors in January 2027NOSBoa's in het ov krijgen toegang tot rijbewijzenregister7sur7Frappé par un cancer du sein, il découvre avoir transmis le gène en cause à son enfant: “Pire que mon propre diagnostic”Het Laatste NieuwsInflatie stijgt in september naar 4,69 procent, gezondheidsindex blijft achter: “Doorsneegezinnen verliezen koopkracht”Hong Kong Free PressHong Kong authorities hail scheme for reducing sodium levels in bread by average of up to 17%Wirtualna PolskaKoniec jesiennej sielanki. Nadciąga gwałtowne załamanie pogodyLa PresseTransports en direct | Rien à signalerChannel News AsiaNepal suspends search after 16 swept away by avalancheynetשליחת "וולט" הותקפה מינית ונותרה לבד: "הם הפנו לי עורף"
The Daily Newsstand · Free, Always
Tuesday, September 29, 2026

Brick shortage prompts $4 million sweetener to get factory reopened

Translate

Western Australian taxpayers will fork out up to $4 million to restart a second brick making facility in the state as the construction industry continues to grapple with labour and raw material shortages.

The state was left with just one brickmaker when Austral closed its Cardup brickworks in mid-2023.

Since then, the government says the number of detached homes starting construction has grown by more than 50 per cent, leaving the remaining manufacturer — Midland Brick — struggling to keep up with demand.

Bricklayers working on scaffolding.

A surge in demand for housing over the last three years, driven by an influx of people into WA, has contributed to the brick shortage.  (ABC News: Keane Bourke)

In an effort to address the shortfall, the state government will now give $3 million to Austral to re-open its facility, which is expected to increase production by up to 15 per cent.

"This is making sure we do everything possible to continue the momentum of building more homes and also reducing the challenges of increased costs [of] bricks," Treasurer Rita Saffioti said.

Rita Saffioti stands in an under-construction home with her hands on her hips.

Deputy Premier Saffioti said the government was helping the industry "get on with it" by providing funding. (ABC News: Keane Bourke)

Asked why state money was required to kickstart the project given the high demand, Ms Saffioti said the government was supporting industries in critical sectors "to get on with it".

"It's as simple as that. We can't have a situation where we know we need to build more houses but simply we don't have the bricks,"

she said.

Labour supply also critical

Industry executives who attended the funding announcement, made at a construction site in the Perth suburb of Sinagra, were unanimous in their support.

"Still not enough, so we've still got an issue, but it's certainly a large help," ABN Group managing director Dale Alcock said.

Dale Alcock speaks at a press conference outside an under-construction home.

Industry veteran Alcock says the Austral plant will go some way towards addressing shortages, but costs remain high. (ABC News: Keane Bourke)

The industry veteran said the company, one of the state's largest homebuilders, had around 100 sites waiting on bricks. He urged the government to look into other ways to increase supply.

Mr Alcock said an "allocation system" used by Midland Brick showed there was "not enough [bricks] currently to go around".

“At the moment, the industry is more concerned about availability than cost,” Mr Alcock said.

"Cost is critical, but without bricks we get no production."

Master Builders WA CEO, Matt Moran, said having a large enough workforce was also critical to the industry's future.

Matt Moran looks through the window of an under-construction home.

Mr Moran wants labour shortages to also be addressed. (ABC News: Keane Bourke)

"We need to double down and invest in trades. We need to promote trades more, attract people to apprenticeships," he said.

No quick fix

The government is offering Austral an extra $500,000 if it can resume operations by March.

The company will also get another $500,000 incentive if it produces at least 17 million bricks in its first year.

However, Housing Industry Association WA CEO, Michael McGowan, warned home owners that this would not provide a quick fix to the delays plaguing the industry, and urged people to be patient over the next 12 months

Michael McGowan speaks at a press conference outside an under-construction home.

Michael McGowan urged homeowners to be patient with the industry, which is still facing delays. (ABC News: Keane Bourke)

"There is going to be a little bit more time before these bricks become available, and the brick layers and the builders are working really hard to deliver the homes that are currently in the pipeline," he said.

Ms Saffioti said the government was still negotiating terms with Austral, including whether the company would be required to keep their facility open for a minimum period.

The view out a large window of an under-construction home.

Housing demand is unlikely to ease any time soon, industry executives say. (ABC News: Keane Bourke)

Mr McGowan said he doubted the company would be lacking in business over the next few years.

"The home building industry is going to be incredibly busy for the next three to four years, and certainly we would encourage this to be a long-term play," he said.

View the original on ABC News (Australia) →