The Jerusalem PostIsrael's strategic depth lies in its global Jewish Diaspora - opinionPunch‘Bamayi’ chant sparks violence as suspected thugs attack APC convoy in GombeInquirerAlmost P15M worth of marijuana bricks seized in Ifugao buy-bustDaily MaverickWHAT WE’RE WATCHING: VisionQuest — Marvel’s latest miniseries has big ideas, but not enough human feelingVariety‘Hanuman Ansh,’ ‘Pyre’ and Shah Rukh Khan Classics Lead International Film Festival of India’s Inflatable Cinema Lineup as NFDC, ESG Renew PictureTime PartnershipGIGAZINE濡れ場に合わせて映画館の座席が動く4DXならぬ4Dセックスが流行、「まるで3人で致したみたいだった」と鑑賞者は語るZDF heuteAktuelle Pressemitteilungen des ZDFNOSHoogste cyberadviseur Trump vertrekt na reeks technische storingenLenta.ruКиев обвинили в попытке сорвать переговоры в ШэньчжэнеScreen RantGTA 6: Should You Choose Saved Cash Or Say Nothing In "Buck Me"Antara NewsPrabowo, Putin hold one-on-one meeting on APEC sidelines in ShenzhenThe Sydney Morning HeraldHe stole our hearts in Severance. Now John Turturro is stealing our wallets
The Daily Newsstand · Free, Always
Friday, November 20, 2026

No sea bridge? Uttan-Virar Sea Link may shift inland; MMRDA plan to cut cost by Rs 20,000 crore

Translate

The Uttan-Virar Sea Link may no longer run through the sea. The Mumbai Metropolitan Region Development Authority (MMRDA) has drawn up two alternative alignments that would take the proposed corridor inland as an elevated road, potentially reducing the project cost by around Rs 20,000 crore — from Rs 58,754 crore to approximately Rs 38,000 crore.

The alternatives on the Uttan-Virar Sea Link were presented to Chief Minister Devendra Fadnavis at a meeting on Thursday. The state government is yet to take a decision on the alignment.

The change is being considered partly to reduce the cost of land acquisition and rehabilitation. The original alignment required the MMRDA to acquire substantial stretches of land, including 104 hectares in Uttan, largely belonging to farmers. The land acquisition process, initiated in July, faced resistance.

A source said the authority had examined whether the corridor could be routed through government land in the region, reducing the need for private land acquisition and rehabilitation. The revised options would take the road inland instead of building the main stretch as a sea bridge.

The original project

The Uttan-Virar Sea Link was conceived as an eight-lane, north-south coastal corridor to connect the northern suburbs of the Mumbai Metropolitan Region (MMR) with the rest of the region. The first phase, spanning 55.12 kilometres, was designed to run from Uttan, near Bhayandar, to Virar, with a 24.35-km sea bridge forming its main component.

The project also included three approach roads: a 9.32-km connector to Uttan, a 2.5-km stretch towards Vasai and an 18.95-km connector to Virar. Together, these stretches were intended to provide access to the sea link from the surrounding urban areas and create a faster north-south road corridor through the western parts of the MMR.

The Virar end of the corridor was also planned to connect with the larger road network leading towards the proposed Vadhavan port in Palghar and the Delhi-Mumbai Expressway. The idea was not merely to provide a shorter route between Uttan and Virar, but to improve regional connectivity and offer an alternative to the congested road network passing through Bhayandar, Vasai and Virar.

Story continues below this ad

The sea link was also part of a larger plan to create a continuous coastal road network along Mumbai’s western edge. This network would bring together the operational Mumbai Coastal Road and Bandra-Worli Sea Link, the under-construction Bandra-Versova Sea Link, the proposed Versova-Bhayandar corridor and the Uttan-Virar link. Once completed, the chain would provide a coastal route connecting South Mumbai with the northern suburbs. The Uttan-Virar project, by itself, would not provide a direct route to South Mumbai; its larger benefit would depend on the completion of the other links.

Second revision

This is the second major cost revision since the project was transferred to the MMRDA by the Maharashtra State Road Development Corporation (MSRDC).

When the MMRDA was entrusted with the 55-km project in 2022, its estimated cost stood at Rs 87,427 crore. The original plan envisaged a 24.35-km sea bridge between Uttan and Virar, along with connecting roads to Uttan (9.32 km), Vasai (2.5 km) and Virar (18.95 km).

The MMRDA then reduced the proposed width of the corridor to bring down construction costs. The main bridge, originally planned with four lanes in each direction, was scaled down to three lanes in each direction, while the connecting roads were reduced to two lanes in each direction. This allowed the authority to plan single-pillar supports instead of two, reducing construction costs.

Story continues below this ad

The revised project, estimated at Rs 58,754 crore, was approved by the state government in November 2025. The MMRDA was exploring funding through the Japan International Cooperation Agency (JICA), for which clearances were sought from the Centre.

However, the land acquisition requirements of the approved alignment remained a challenge. The authority has since examined two alternatives that would use government land and reduce the extent of rehabilitation.

The meeting on Thursday was attended by MMRDA metropolitan commissioner Sanjay Mukherjee, additional commissioner P Velarasu, additional chief secretary Aseem Kumar Gupta, BMC commissioner Ashwini Bhide, Thane municipal commissioner Saurabh Rao, Mumbai joint commissioner of police Deven Bharti and the Chief Minister’s chief economic and investment advisor Kaustubh Dhavse, among others.

The MMRDA also presented the proposal for Pataal Lok, a 31-km integrated tunnel network intended to connect the Bandra-Worli Sea Link, Bandra-Kurla Complex, Terminal 2 of the Mumbai airport, the Western Express Highway and the Eastern Express Highway.