Daily MaverickRISING RED TIDE: Communism is growing – How tenderpreneur frustration gave the SACP a new support baseCNN Türkİran'dan yeni füze fırlatma sistemi! "İki sıvı yakıtlı füzeyi aynı anda ateşleyebiliyor"PunchFG may raise N20,000 NELFUND student allowance — OfficialInquirer EntertainmentBTS dominates two-day 2026 MAMAs with five winsThe Jerusalem PostDefense officials reject Treasury warning over NIS 100b. shortfall in US arms dealstazHistoriker über Weihnachten: „Die Elemente kommen aus unterschiedlichen Quellen“한겨레‘AI 커닝’ 의혹, 엠디트 수석까지…“6년 준비” 반박VanguardLokpobiri celebrates Youth Minister Olawande’s weddingZDF heuteAktuelle Pressemitteilungen des ZDFRTL BoulevardDit is Remi! Jezelf kunnen zijn, mogen zijn, durven zijnVarietyKarla Sofia Gascon Says ‘Emilia Perez’ Oscar Controversy Came From People Who ‘Didn’t Want Someone Like Me to Receive an Award’NOSDroneaanval op woongebouw Kyiv: twee gewonden, mogelijk mensen onder puin
The Daily Newsstand · Free, Always
Sunday, November 22, 2026

'One-in-2,000-year weather' to be investigated post-blackout

Translate

The SA government says the suggestion that a "one-in-2,000-year weather event" was responsible for the Eyre Peninsula blackout will be critically examined amid ongoing fallout from the incident.

Electricity supply to the peninsula and the state's West Coast was cut on Thursday afternoon when two transmission towers collapsed and a third was severely damaged during intense storms, leaving more than 20,000 properties without power.

Power was gradually restored to most of those properties over the following 24 hours, but the blackout has again raised the question of energy security, 10 years on from the 2016 statewide blackout.

ElectraNet — which is responsible for the state's high-energy transmission lines — on Sunday confirmed it was conducting a "complete and thorough review" into the recent outage.

On Friday, the company suggested the towers were likely brought down by a "one-in-2,000-year weather event" — a contention SA Premier Peter Malinauskas said would be considered during investigations into the incident.

"There are one of two possibilities here," Mr Malinauskas said.

"Either this was a genuine 'one-in-2,000-year weather event' here that understandably nothing can withstand — or, two, something went wrong in terms of the specifications of that infrastructure.

"That's what the investigation will examine, and that's what we're very keen to look at before we rush to make a judgement."

A large transmission tower lays across the ground after being toppled

ElectraNet says two towers were downed and a third sustained major damage. (ABC News: Stephen Opie)

The high-voltage transmission line along which the towers collapsed was completed only a few years ago, at a cost of $300 million.

ElectraNet executive Alex Trento told 891 ABC Adelaide on Friday the transmission towers were "built to a one-in-2,000-year weather event", and to withstand wind speeds of up to 172km/h.

"What we think has occurred is that the weather in this localised region has been even stronger than the winds that it was designed for,"

Mr Trento said.

He said ElectraNet was "always in contact with the bureau" but said there was no advance warning of an event on the scale of what occurred on Thursday.

But he added that what had occurred was "a very unique, very rare occurrence in a very localised area".

"I don't think we could have done anything better from that perspective."

'No evidence of tornadoes'

The Bureau of Meteorology said while wind speeds of around 100km/h were recorded at Roxby Downs on Thursday, gusts of around 170km/h were "unlikely".

"When we're talking wind gusts of more than 170km/h — those are the wind gusts you typically only see in tropical cyclones or associated with tornadoes," senior meteorologist Jonathan How said last week.

"There was no evidence of tornadoes that we could see [on Thursday] across the Eyre Peninsula.

"So certainly, 170km/h is something we couldn't really confirm. It's probably unlikely at this stage because the state record for South Australia is 167km/h. That was set in Woomera back in 1979."

The images of collapsed and damaged towers at Wharminda on Eyre Peninsula are reminiscent of the scenes that accompanied the 2016 statewide blackout, when towers were felled in the state's mid north.

At a media conference on Friday afternoon, Mr Trento said that following the 2016 event, transmission line design standards were improved.

A fallen transmission tower near Melrose in South Australia's north.

A fallen transmission tower near Melrose in South Australia in 2016. (ABC News: Dean Faulkner)

Asked whether there was a structural fault in the new towers, Mr Trento conceded that was a possibility, but expressed confidence that the towers had been constructed in accordance with the appropriate standards.

"We are investigating … but at this point in time, seeing the localisation of the event, we do think that the towers have been designed and constructed effectively,"

he said.

"We think the wind that has entered those towers has been above the specification that we've constructed it to.

"We could have been looking at a 250km/h wind session. We just don't know."

View the original on ABC News (Australia) →