ESPN DeportesRays arma rally y pone contra la pared a Yankees en SDLAThe Jerusalem PostIsrael must be ready for any threat, no matter how unthinkable it may seem - editorialInquirerImpeachment court opens VP Duterte’s P4.4-B transaction docsESPNBijan Robinson, Falcons make NFC South statement in rout of SaintsZDF heuteEntdecken Sie das ZDF-NachrichtenstudioCNN TürkHava Durumu (06-10-2026)Sky TG24Guerra Ucraina Russia, nella notte centinaia di droni sulla regione di Mosca. LIVESözcüAkaryakıt devinde deprem: Benzin zammı şirketi sarstı, CEO görevi bıraktıCapital FMEthiopian rebel forces withdraw from Tigray regional capitalRapplerAccenture contractor removed from FBI following damaging data breach, sources sayn-tv44 Mann - und nun?: Klopps erschreckendste Erkenntnis könnte die Neustart-Chance seinSRF NewsTrockenheit und Futternot – Wenn das Futter knapp wird: Mehr Tiere in der Auktion
The Daily Newsstand · Free, Always
Tuesday, October 6, 2026

North-South Corridor delay: Affected business to continue getting HDB rental rebates if eligible

Translate

SINGAPORE: Businesses in Housing and Development Board (HDB) rental shops that are most affected by the North-South Corridor delay will continue to receive rental rebates where there are grounds to do so, said Transport Minister Jeffrey Siow in parliament on Tuesday (Oct 6). 

Several Members of Parliament (MPs) had asked about the impact of the delay, and if additional financial support could be given to affected businesses and residents.

"Several businesses in HDB rental shops most affected by the construction works have been receiving rental rebates on a case-by-case basis. HDB will continue to extend these rebates where there are grounds to do so," said Mr Siow.

"But as a general principle, the government does not compensate stakeholders for project delays."

Doing so would add significant upfront costs to these projects, since the government would have to insure against "multiple unknown scenarios", he added. 

"But that does not mean we are leaving businesses and residents to fend for themselves," he said.

After the Land Transport Authority (LTA) announced in September that the opening of the North-South Corridor will be delayed by two years due to unexpectedly challenging ground conditions, businesses near the North-South Corridor construction sites told CNA they were concerned about survival. 

The project was originally expected to cost S$7.47 billion (US$5.8 billion). Responding to questions about the costs of the delay, Mr Siow said that it would likely result in a higher project cost, reiterating what LTA said in September. 

Since LTA is still assessing the extent of permissible claims by contract, it cannot provide an updated project cost at this point and will do so later, he added. 

TIMELINE FOR SURFACE WORKS

The viaduct section, from Admiralty Road West to Lentor Avenue, is now expected to open in phases from 2029, instead of 2027 as previously announced. The tunnel section from Lentor Avenue to East Coast Parkway is now expected to open in phases from 2031, instead of 2029.

Mr Siow noted that residents’ concerns about noise, dust and disamenities are generally caused by construction works on the surface. 

“I have asked LTA to prioritise the completion of surface works, so that surface conditions start to improve from next year onwards,” he said. 

Most of the major structural works that create the most noise and dust should be completed by the end of 2027, he added. 

After that, LTA will reinstate roads, footpaths and other affected spaces from 2028. For example, the surface for Lentor Avenue and Sembawang Road should be fully restored by mid-2028, said the transport minister. 

“I have also asked LTA to pay particular attention to businesses along the construction route,” he added. 

Changes to pedestrian routes or road access affect customer traffic for neighbourhood businesses, he said, adding that LTA has installed signs and banners to guide customers to affected businesses. 

When surface works are completed, many access routes for pedestrians will be restored as a priority, said Mr Siow. 

LTA will also try to introduce more direct walking routes to shops and food and beverage outlets to make it easier for customers to reach them, he added. 

"We will do everything in our power to ease the friction on the ground. At the same time, I ask for your understanding to give our engineers and workers the time and space required to complete the remaining works safely," he said.

View the original on Channel News Asia →