Punch2027: Tinubu can’t save Alli, Yayi, Hamzat – OppositionDaily MaverickPop star Miley Cyrus weds drummer Maxx Morando in CaliforniaInquirerClosure, full justice still elusive 17 years after Maguindanao massacreThe Jerusalem PostAlice Huang in touch with Chinese spy agency during affair with Nvidia CEO - report한겨레반도체 흑자가 네덜란드병 초래?…환율이 다른 수출산업 가격경쟁력 떨어트려Inquirer EntertainmentBea Millan-Windorski seals Miss Universe frontrunner status with prelims performanceZDF heuteEntdecken Sie das ZDF-NachrichtenstudioKhaosod EnglishBangkok, six central provinces warned of flooding as high tides approachDaily MailBritney Spears unleashes on her exes as she claims they all urged her to 'get surgery' and 'hair implants' to fix her 'big' foreheadThe Straits TimesSingapore, China reach 29 deals at top bilateral forum경향신문밀양·창녕 5곳, 문체부 ‘열린관광지’ 선정···경남 35곳으로 확대Lenta.ru22-летний россиянин потерял свободу на 13 лет из-за предложения в интернете
The Daily Newsstand · Free, Always
Monday, November 23, 2026

RM780,000 sought to repair streetlights damaged by cable theft in Putrajaya

Translate

KUALA LUMPUR: A RM780,000 funding application to repair streetlights affected by cable theft along Federal Routes FT29 and FT30 in Putrajaya has been deferred to a subsequent phase of implementation.

Deputy Works Minister Datuk Seri Dr Ahmad Maslan said the application was submitted in March this year, but implementation would depend on the ministry's funding priorities.

"The road safety infrastructure upgrading programme prioritises small-scale, targeted streetlight installations at accident-prone locations or areas posing risks to motorists due to poor lighting," he told the Dewan Rakyat.

He was responding to a question from Datuk Dr Radzi Jidin (Bersatu-Putrajaya) on the maintenance of streetlights and road markings along FT29 and FT30, including the use of solar-powered streetlights in areas frequently affected by cable theft.

Ahmad said priority would be given to high-risk locations such as junctions, bends and bridges, based on accident records and lighting requirements.

He said the Works Ministry allocated RM840,000 in 2025 under the Peninsular Malaysia Federal Road Maintenance Programme for seven streetlight maintenance projects.

"The works have been completed along several routes around Kuala Lumpur International Airport (KLIA), FT29 and FT30, including the slip roads at Persiaran APEC, Putrajaya Sentral, the National Cancer Institute and Persiaran Selatan," he said.

Ahmad said road marking works along both directions of FT30, costing RM1 million, were completed on Oct 31.

He said the project, carried out under Phase Two of the Non-Routine Pavement Maintenance Programme, began on Aug 12 this year to improve road safety.