The Jerusalem PostTurkey sending technical, defensive support to Saudi Arabia to help fight Houthis, officials sayESPNAre Texans and Chargers this bad? How should we bet the Rams?ESPN DeportesGurú de las Diagonales: El misterio en torno a Drake MayeBollywood HungamaSCOOP: Ramayana expected to have paid previews on November 4; Godzilla Minus Zero to get limited showcasing in IMAX in IndiaDaily MaverickLABOUR ABUSE: New report exposes the exploitation behind the world’s food systems workersInquirerMan nabbed after surrendering unlicensed firearm in Oriental MindoroZDF heuteEntdecken Sie das ZDF-NachrichtenstudioThe South AfricanSaleng spotted back in Sundowns training ahead of Pirates showdownBBC Sport'Draining' few days for Gauff after online racist abuse01netAmazon éclate le prix de ce PC portable Dell : -45% pour finir le Prime Day en beautéRai NewsCile, cane randagio salvato dalla piena del fiume MapochoSBS 뉴스"우리 대응에 북한 당황"…"지뢰 제거, 단호한 대응이냐"
The Daily Newsstand · Free, Always
Wednesday, October 7, 2026

Finland orders Google to halt work on two data center projects

Translate
Google"s headquarters in Silicon Valley in Mountain View, California.

JHVEPhoto/iStock Editorial via Getty Images

Finnish authorities have ordered Google (GOOGL) to halt certain preparatory work on two data center projects in the country until environmental impact assessments are completed, less than a month after the company announced a $15B investment in Finnish AI infrastructure.

The Finnish Licensing and Supervision Agency, known as LVV, issued the notice to Tuike Finland Oy, Google's Finnish subsidiary, covering planned data centers in Muhos and Kajaani.

Google did not immediately respond to Seeking Alpha's request for a comment.

The agency said the data center work must be suspended immediately and no later than Oct. 23. The order covers activities including tree removal, topsoil removal, excavation, quarrying, crushing, moving soil, ditching, and construction of roads and storage areas.

The agency said extensive preparatory work had already been carried out at the sites and could change the environment before the environmental impact assessments were completed. It said the assessments are intended to identify and evaluate significant environmental effects before major decisions and preparatory work are undertaken.