Daily MaverickARTFUL REPOSE: At home with African art: resting in a museum of creative repairInquirerNKTI’s 12-story extension ‘operational’ by 2028The Jerusalem PostRequests for sexual assault support jump 28% as survivors face treatment backlog한겨레경찰, ‘선거법 위반 혐의’ 성주군수 휴대폰 압수수색Inquirer EntertainmentKlea Pineda reveals wedding talks with Janella Salvador: ‘Beach wedding’ZDF heuteAktuelle Pressemitteilungen des ZDFSözcüABD’de dijital kaos! Uçuşlar durdu, bankalar aksadıNHK 社会【動画】Pickup NEWS(11月18日)The Sydney Morning HeraldBuilding Bad royal commission LIVE updates: Bikie Joel Leavitt says dull safety paperwork was easier after ‘a big line’ of cocaineNew Straits TimesCourt overturns adoption order involving foreign nationalQuemEx-BBB Eslovênia celebra seus 30 anos e avalia: 'Toda escolha exige renúncias'HabertürkAşıklar ilk kez görüntülendi
The Daily Newsstand · Free, Always
Wednesday, November 18, 2026

MP flags environmental, water concerns over Kapar industrial park

Translate

KUALA LUMPUR: An opposition member of parliament (MP) has asked whether the government had assessed the combined impact of a planned 1,623-acre industrial development in Bukit Kerayong, Kapar, on flooding, water supply, electricity and infrastructure.

Dr Halimah Ali (PN-Kapar) raised the concerns in a supplementary question to Deputy Digital Minister Datuk Wilson Ugak Kumbong in the Dewan Rakyat.

She asked whether an assessment had been carried out to ensure the project would not worsen flooding or increase the risk of overflow because of changes in land use.

Halimah said Kapar already faced infrastructure problems, including overcrowded schools, recurring floods, damaged roads and pressure on its drainage system.

She also asked whether the government could ensure residents would not bear the social and environmental costs of the project while others benefited from the investment.

According to a YTL Power International statement issued on Oct 29, the company had entered into a joint venture with SD Guthrie and Bumi Assets to develop the industrial site.

An online report said MBSB Research had not ruled out the possibility of a large-scale data centre campus being part of the development.

Ugak said the Data Centre Task Force assessed every data centre application to ensure adequate electricity and water supplies before approval.

He said the assessments were carried out in coordination with utility providers and relevant technical agencies.

The government also assessed energy efficiency through Power Usage Effectiveness and encouraged the use of renewable energy and more efficient technology, he said.

View the original on New Straits Times →