The Jerusalem PostMecca Pact condemnation of Houthi attacks shows Turkey-Saudi-Pakistan ties are improving - analysisPunchHealth practitioners urge Jigawa to recruit more staff, improve welfareVanguardAtiku, Obi relying on regional support to win election, Shettima saysFutura SciencesPendant 7 ans, un télescope observe une planète géante : en 2026, elle disparaît de ses mesures, et une autre planète serait responsableNOSKoffers tjokvol wiet: twee Nederlanders opgepakt op luchthaven BoedapestMeduzaВ Австрии повторно арестовали двух сотрудников украинской военной разведки. Их подозревают в шпионаже и попытке похищенияESPNLakers taught important playoff lesson by Spurs: Co-stars matterBBC Mundo"Ni EE.UU. llegó tan lejos": por qué Costa Rica le impidió la entrada al país a Francesca Albanese, relatora especial de la ONU para los territorios palestinosGuardian SportManchester United v Brentford, Leeds v Coventry and more: Saturday football clockwatch – liveIl Fatto QuotidianoAlbania, migliaia di persone ancora in piazza contro il governo: scontri tra polizia e manifestanti a TiranaFox NewsTSA agent spots strange detail on scanner, finds dangerous object inside SharpieSeeking AlphaInsider Trades: Palantir, Walmart, Home Depot among notable names
The Daily Newsstand · Free, Always
Saturday, November 28, 2026

You are reading Joho no Todai on KioskNews: newspapers from many countries on one stand, each linked to its original. What other papers report

Belgium Orders Google to Stop Data Center Construction After Work Continued Without a Permit

Translate

Authorities in Belgium's Walloon Region ordered Google to stop work on a data center. A Greenpeace investigation found construction had continued after the permit was revoked. The regional government is preparing a report for prosecutors.

A 30,000-square-meter building nearly took shape without a permit

Walloon authorities sent inspectors to Google's construction site in Aiseau-Presles, near Charleroi, on November 26, local time. Belgian public broadcaster RTBF reported that regional official Raphaël Stokis described what inspectors found.

The shell of a 30,000-square-meter building covering three hectares was nearly complete despite the minister refusing permission. About 300 workers were on site. Inspectors issued a verbal stop-work order, to be followed by written notice to Google.

The facility is being built in a 50-hectare business park on a former coal mine. About three months had passed since the permit was revoked.

Three days before the inspection, Greenpeace Belgium used satellite images as the basis for a letter asking the Walloon government to stop work immediately. The group said it investigated after hearing from residents and found that construction had continued after the permit was revoked.

A switch from air to water cooling drew objections

Google obtained permission in 2024 to build three data center buildings in Aiseau-Presles. The original plan called for air cooling.

In 2025 Google applied to combine two of the three buildings into a larger facility and switch to water cooling. It planned to draw 600 cubic meters of water per hour from the nearby Sambre River. Walloon authorities approved the changes in April 2026.

Changes to the Aiseau-Presles data center plan

Original plan (2024)Revised plan (2025)
CoolingAir coolingWater cooling (Sambre River)
Facility sizeThree buildingsTwo buildings combined into one
Water withdrawal—600m³ per hour
Regulatory decisionPermittedApproved → revoked

※600m³ refers to water withdrawn.The full volume is not consumed.

Residents objected the following month. As Belgium faced a historic summer drought, Walloon infrastructure minister François Desquesnes revoked the amended permit in August. A Greenpeace Belgium statement says he specifically cited the data center's water demand.

For scale, Greenpeace Belgium says Google's existing data center in Saint-Ghislain draws a billion liters of water a year for cooling, of which three-quarters evaporates.

Work continued after the permit was revoked.

A report to prosecutors and a January 2027 hearing

Google appealed the revocation to Belgium's Council of State on October 17, local time. A public hearing is scheduled for January 7, 2027, local time. Residents and Greenpeace applied to join the proceedings on November 16, local time.

The Walloon government is pursuing legal steps after the stop-work order. Regional government spokesperson Nicolas Yernaux told AFP on November 27, local time, that the process of submitting a violation report on unauthorized construction to prosecutors was underway.

Timeline from permit to stop-work order

2024

Permit granted for three buildings

Air cooling planned

2025

Google requested changes

Two buildings combined, air → water cooling

April 2026

Authorities approved amended permit

May 2026

Residents filed an objection

Concerns over water drawn from the Sambre

August 2026

Minister revoked amended permit

Cited drought and the data center's water demand

October 17

Google appealed to the Council of State

Sought to annul and suspend the permit revocation

November 23

Greenpeace asked authorities to halt construction

Letter cited satellite images

November 26

Authorities ordered work to stop

Shell of the 30,000m² building nearly complete

November 27

Violation report in preparation

Unauthorized construction to be reported to prosecutors

January 7, 2027

Council of State public hearing (scheduled)

※Dates are in Belgian local time.

Google said it had followed the authorities' instructions, stopped work, and was awaiting further direction.

Google said it had stopped work as instructed and was waiting for further direction. It said it had operated in Belgium for more than 15 years and was committed to complying with local law and continuing to work openly with Walloon officials and regulators.

Greenpeace Belgium welcomed the stoppage. Spokesperson Nadia Cornejo said it should have happened when the permit was revoked in August and called it a first win for residents and the environment. The group plans to keep monitoring the project.

Other European countries have seen disputes over Google's data centers. In Finland, a criminal investigation into possible environmental violations began in October, and work has stopped pending an environmental impact assessment.

Similar disputes are emerging in Japan

Data center construction has also drawn local opposition in Japan. Noise, exhaust emissions, and inadequate advance notice have led to disputes with residents around the country.

At a November 20 press conference, Japan's minister of economy, trade and industry, Ryosei Akazawa, said the ministry intended to produce an action plan by year-end to promote data center siting and address local concerns. He said direct water withdrawals are governed by laws and local ordinances, and the ministry would monitor the situation with other agencies.

The Belgian stoppage shows how much more data center expansion requires beyond a building plan and a power supply. Cooling design, water resources, community agreement, and permits all matter. A problem with any one of them can halt a 30,000-square-meter building even when it is nearly complete.

View the original on Joho no Todai →