InquirerPangasinan towns revoke class suspensions for Teachers’ DayCNN TürkAvrupa panikte: Dünya ekonomisinin çarkını döndüren dizel alarm veriyorThe Jerusalem PostUS military strike kills four suspected narco-terrorists in Caribbean as campaign toll tops 220Bollywood HungamaJanhvi Kapoor condemns morphed AI video from Devara Part 1 song ‘Chuttumalle’: “Consent, choice and respect for a woman's body should be basic”PunchNew Army formations will strengthen response to insecurity — TinubuESPNChourio adds to burgeoning Brewers legend with walk-off single in Game 2Daily MaverickBOOK EXTRACT: My best friend, ED: Evolution of an eating disorder from childhood into adulthoodESPN DeportesWhittaker domina a Wallace y sobrevive a un cierre caóticoCapital FMGovt activates national response as El Niño rains approach KenyaZDF heuteAktuelle Pressemitteilungen des ZDFIl Fatto QuotidianoLa forza di un no!, ecco cosa emerge dal report pilota sulle vittime di matrimoni forzatiRTL BoulevardDries Roelvink leeft mee met liefdesverdriet van zoons
The Daily Newsstand · Free, Always
Monday, October 5, 2026

Kuala Nerus coastal erosion project delayed 144 days, says AG Report

Translate

KUALA LUMPUR: The Kuala Nerus Coastal Erosion Control Project in Terengganu was delayed by 15.7 per cent, or 144 days, due to a shortage of machinery and delays in obtaining Environmental Impact Assessment (EIA) approval.

Auditor General Datuk Seri Wan Suraya Wan Mohd Radzi in the AG Report 2/2026 tabled in Parliament today said there was also no construction activity at Breakwaters No. 1, 2, 3 and 9.

She said the delay in obtaining EIA approval affected the beach nourishment component of the project.

"The audit found weaknesses in the implementation of the Kuala Nerus Coastal Erosion Control Project, with a delay of 15.7 per cent, or 144 days, due to a shortage of machinery and the absence of construction activities at Breakwaters No. 1, 2, 3 and 9, as well as delays by the contractor in obtaining EIA approval for the beach nourishment scope," she said in a statement

Wan Suraya said coordination between the Public Works Department and the Department of Irrigation and Drainage should be strengthened to ensure Breakwaters No. 7 and 8 were completed promptly before the Northeast Monsoon.

"This is to prevent the collapse of roads that have already been repaired," she said.

Meanwhile, the audit found that the nationwide Coastal Conservation Programme had achieved its objectives based on 10 completed projects.

The programme had helped protect vulnerable coastal areas from erosion, reduce the risk of coastal flooding and provide navigational channels.

The Auditor General's Report 2/2026 comprises 15 documents covering government finances and activities.