Promised in 10 days, parcel to Canada took 28 days; courier firm ordered to pay Rs 58k
![]()
AI generated image used for representative purpose
NEW DELHI: A consumer commission in Haryana has held a courier company guilty of deficiency in service for delivering a shipment of clothes and edible items to Canada 28 days after accepting it, despite assuring delivery within 10-12 days.The commission directed Brand House to pay Rs 48,400 towards the value of the edible items and courier charges. It also ordered the firm to pay Rs 10,000 as compensation and litigation costs.In its November 5, 2026, order, the District Consumer Disputes Redressal Commission, Rohtak, noted that the delay had defeated the purpose of sending the seasonal clothes and perishable food items to Canada.
Courier firm delays delivery of food items and clothes to Canada
According to the commission order, Surender Dhokal, a 47-year-old advocate from Rohtak, had booked the services of Brand House on January 29, 2025, to send clothes and edible items to Canada.The shipment was booked on January 30, 2025, under tracking ID 1Z0V1Y572017007517. The complainant handed over the items to the firm's representative in Rohtak and was assured that they would be delivered within 10-15 days. He paid Rs 18,400 for a shipment weighing 21 kg through UPI.However, the complainant said the items were not delivered within the promised period. He claimed that the clothes were meant for the winter season and would become useless after the season ended.
The edible and perishable items also became stale or unusable because of the delay. He valued the items at Rs 50,000.The complainant said he contacted the firm several times but did not receive a satisfactory response. He also sent a legal notice on February 27, 2025, but received no relief.He approached the commission seeking Rs 3 lakh for non-delivery within the promised period, Rs 50,000 as compensation for harassment and Rs 22,000 towards litigation expenses.Brand House did not appear before the commission despite receiving notice. It was proceeded against ex parte through an order dated May 22, 2025, and did not file its defence.
Why commission held courier firm liable
The bench comprising president Nagender Singh Kadian and members Dr Tripti Pannu and Dr Vijender Singh noted that the complainant had submitted payment details, shipment documents, delivery receipt and WhatsApp conversations with the firm.The commission observed that the WhatsApp chats showed that the firm had assured delivery of the perishable items within 10-12 days. However, the delivery receipt showed that the shipment was delivered only on February 28, 2025, after 28 days.It said the delay could have made the perishable items stale, inedible or unusable. The clothes, too, could not serve their intended purpose because they were not delivered during the relevant season.The bench also noted that the firm had failed to appear despite service of notice, leaving the complainant's evidence unrebutted.“Perusal of the documents reveals that the items were delivered on 28.02.2025, i.e. after 28 days, as against the assured delivery period of 10-12 days. Due to such delay, the perishable items might have become stale, inedible or otherwise unusable. Further, the clothes, having not been delivered within the stipulated time, could not serve the intended purpose of the consignee at the relevant time,” the commission said.
The commission further recorded that the complainant had submitted during arguments that the shipment included 10 kg of desi ghee laddus, valued at around Rs 30,000, considering the cost of desi ghee and dry fruits. He had also paid Rs 18,400 as courier charges.Considering the delay and the resulting loss, the bench said it would be just and proper to award Rs 30,000 towards the value of the edible items and Rs 18,400 towards courier charges.
Final order
The commission allowed the complaint and directed Brand House to:
- Pay Rs 48,400 towards the value of the edible items and courier charges, along with 9 percent annual interest from March 27, 2025, until realisation.
- Pay Rs 5,000 as compensation for mental agony and harassment.
- Pay Rs 5,000 towards litigation expenses.
- The firm has been directed to comply with the order within 30 days of receiving a copy of it.
KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.