Inquirer5 fishermen nabbed for alleged blast fishing in Occidental MindoroThe Jerusalem PostMassive overnight Russian attack leaves over half a million Ukrainians without power, Zelensky saysPunchEPL: Raya proud of Arsenal’s ‘incredible’ reaction after third straight winDaily MaverickBrazil’s Bolsonaro, Lula spar in first debate as personal attacks flyBusiness AMPoetin versterkt de luchtverdediging van zijn luxueuze landgoed in Valdai tegen dronesZDF heuteEntdecken Sie das ZDF-NachrichtenstudioThe South AfricanKaizer Chiefs rumours: Maboe, Leaner bust-up, Da Cruz’s failed experimentIl Fatto QuotidianoPerché le proteste dei giovani hanno ragione di esistereVarietyLucca Comics Chief Emanuele Vietina on Celebrating the Crossover Between Movies and Video Games: ‘It’s All Part of a Specific Vision’RTL Boulevard'Verwoestende' represailles voor EU als het Starlink beperktNHK 社会神奈川 藤沢 乗用車がバスなど次々に衝突1人死亡13人けがScreen RantCall Of Duty: Modern Warfare 4 Players Need To Change This Setting For A Key Advantage
The Daily Newsstand · Free, Always
Monday, October 19, 2026

Deputy minister: No payment delays affecting Pan Borneo Highway project

Translate
There have been no delays in payments to contractors working on the Pan Borneo Highway project that could affect construction progress, Deputy Works Minister Datuk Seri Dr Ahmad Maslan told the Dewan Rakyat today. — Bernama pic

There have been no delays in payments to contractors working on the Pan Borneo Highway project that could affect construction progress, Deputy Works Minister Datuk Seri Dr Ahmad Maslan told the Dewan Rakyat today. — Bernama pic

First Published: Monday, 19 Oct 2026 4:03 PM MYT

KUALA LUMPUR, Oct 19 — There have been no delays in payments to contractors working on the Pan Borneo Highway project that could affect construction progress, Deputy Works Minister Datuk Seri Dr Ahmad Maslan told the Dewan Rakyat today.

He said payments for Phases 1A and 1B were being made in line with physical progress, with disbursements keeping pace with or exceeding scheduled levels.

“Phase 1A, comprising 15 work packages, had achieved 89.54 per cent physical completion against a scheduled 96.23 per cent, while financial disbursements stood at 88.78 per cent.

“For Phase 1B, which has only recently begun, actual physical progress stands at 25.53 per cent, ahead of the scheduled 24.76 per cent.

“Financial disbursements have reached 22.11 per cent, exceeding the scheduled 20.73 per cent. Therefore, there is no issue with payments,” he said in reply to Datuk Wetrom Bahanda (KDM-Kota Marudu) on whether delays in the project were caused by late payments to contractors or the appointment of contractors lacking the necessary expertise.

Ahmad also acknowledged that contractor performance remained a concern that needed to be addressed to keep the project on track.

He said the Works Ministry had tightened monitoring through monthly meetings to review construction progress and resolve emerging issues.

The meetings, chaired by the Sabah State Secretary and the ministry’s Secretary-General, were part of efforts to ensure the project was implemented effectively, he said.

The ministry has also introduced measures to prevent further delays, including strengthening steering committees and special task forces to assess contractor performance, identify causes of delays and develop solutions.

These measures are aimed at ensuring the Pan Borneo Highway project is completed on schedule, he added. — Bernama