ESPNJaxson Dart's coming at you from all angles: 'He's got exceptional arm talent'ESPN DeportesIsaac del Toro conquista a rivales y aficionados en el MundialInquirerBody of missing Apayao resident found after 3 days of searchThe Jerusalem PostMassive US flight groundings triggered by fiber cut, circuit failure as UN General Assembly meetsCNN Türkİletişim Başkanı Duran: Türkiye-ABD ilişkilerinin tarihi, geçen yüzyıl dünya tarihinin özeti niteliğindePunchIdris, Malami camps battle over ex-minister’s suitability for Kebbi jobוואלהטראמפ לממדאני: "ראיתי ראשי עיר מצוינים וכאלה שפחות. מקווה שתהיה אחד מהמצוינים"Inquirer EntertainmentLove Knots, September 22, 2026한겨레12년 만의 금메달 목에 걸고…남자농구 24일부터 시범경기UOLAprovação de Donald Trump cai a 32% e volta a atingir mínima históricaEl Comercio¿Cómo saber si eres miembro de mesa para las Elecciones Regionales y Municipales? Consulta con tu DNI
The Daily Newsstand · Free, Always
Tuesday, September 22, 2026

Texas Governor Abbott halts all state-issued permits for data centers until grid audit is complete

Translate

HOUSTON, Sept 21 : Texas Governor Greg Abbott on Monday barred the state's environmental agency from issuing new permits for data centers until regulators complete a massive audit of the energy-hungry facilities seeking to connect to the Texas electrical grid.

The Republican governor's directive to the Texas Commission on Environmental Quality effectively freezes all state-issued permits for data centers. 

Since the artificial intelligence boom began roughly three years ago, Texas has become one of the fastest-growing data hubs in the world. But growing public backlash over the facilities, and fears about AI more broadly, prompted Abbott last month to freeze the connection of new data centers to the state grid and order an audit of the facilities.

Those connections are now pending an audit by grid regulators, which have been directed to examine data center power use, tax incentives, end users and water consumption, among other factors.

“Simply put, Texans must come first,” Abbott said. “Data centers must pay their own way, protect our grid and water, and complete the (audits)," Abbott said in a statement. 

Texas grid regulators have estimated that their audit of data centers could last until late next year. 