The Jerusalem PostTwo Libyan army personnel succumbed to wounds after Ukrainian attack on Benghazi portPunchPete Edochie’s death a loss to Nigeria, Africa – ObiCNN TürkTeknolojinin yeni hali akıllı küpeInquirer EntertainmentMiss Universe 2026 kicks off coronation showInquirerMinSU-Victoria tops Sept. 2026 LET secondary levelZDF heuteAktuelle Pressemitteilungen des ZDFGIGAZINE「Firefox 161」正式版リリース、閲覧データを素早く消去できるボタンが登場&内蔵VPNがサイトごとに設定可能にGolem.deNvidia: Jensen Huang lehnt Nachfolgeregelung abTagesschauDeutsche Wirtschaft wächst im dritten Quartal nur um 0,1 ProzentPolsat NewsPoważna awaria na kolei w Warszawie. Opóźnione i przekierowane pociągiObservador DesportoPorto. Moradores afetados pelo TGV têm de sair de até junhoMyJoyOnlineEcobank, Mobile Money Fintech Ltd launch cross-border MoMo transfers between Ghana and Côte d’Ivoire
The Daily Newsstand · Free, Always
Wednesday, November 25, 2026

Construction underway on temporary transmission towers for Eyre Peninsula

Translate

The southern Eyre Peninsula is expected to be reconnected to the national electricity grid by Friday morning, after storm activity last week downed two transmission towers and severely damaged a third.

More than 20,000 properties on the peninsula and West Coast lost power on Thursday during the severe weather, and while construction has begun on temporary towers, operators say it could take a year for permanent structures to be installed.

The damaged towers were located on a farm at Wharminda, which sits along a 270-kilometre transmission line between Port Lincoln and Cultana.

A truck trailer with several solid cement cubes, a crane lifting one up, a workman standing nearby

Construction of four temporary transmission towers has began. (ABC Eyre Peninsula: Jodie Hamilton)

Electricity transmission operator ElectraNet said local generation restored power for Port Lincoln and surrounding areas on Thursday night, and the network had to be reconfigured to allow services to return to some other parts of the Eyre Peninsula.

Following their installation, the four temporary towers would need to be tested before being re-energised, which would restore transmission services from Cultana to Port Lincoln.

ElectraNet chief executive Simon Emms said he was hoping services would be operational by early Friday.

Two men standing infront of microphones in a paddock, wearing high-vis shirts and hard hats

ElectraNet's Alex Trento and Simon Emms spoke from the Eyre Peninsula on Wednesday. (ABC Eyre Peninsula: Jodie Hamilton)

"We're actually going to put up temporary towers each side of the existing line route, and then route the existing conductors around that," he said.

"The current line is down, the temporary towers are lying flat, they'll be erected today."

SA Power Networks had advised residents in and around Port Lincoln of a planned power outage occurring on Thursday night while the region is reconnected to the transmission network.

Mr Emms said the temporary towers have been built to the same standard as the current line.

ElectraNet confident in tower design

Mr Emms said on Wednesday the three transmission towers were damaged by a "localised, very severe wind event", and he was confident they had been built to the right strength.

"We know the towers are designed to the appropriate Australian standard. That design has been checked, independently checked, and we also built a test tower and tested it to destruction," he said.

"To the best of our knowledge, it's purely that the winds were stronger than the towers were designed to withstand."

Mr Emms said ElectraNet would undertake a "thorough and complete" investigation into the incident.

Following the storms last week, ElectraNet had suggested the towers were likely brought down by a "one-in-2,000-year weather event", something the SA government said would form part of investigations into the incident.

A crumpled transmission tower in a column of other towers.

Damage to ElectraNet's transmission towers on the Eyre Peninsula. (ABC News: Steve Opie)

Mr Emms said new permanent transmission towers would need to be built in place of the three damaged structures, which he estimated could take up to a year.

"One of the longest lead times is actually getting all of the right steel together to build that," he said.

ElectraNet executive Alex Trento said Port Lincoln residents would need to continue to leave their rooftop solar inverters off until told otherwise, to prevent the generator coming offline before the transmission line had been restored.