The Jerusalem PostIDF confirms vehicle struck in Gaza was used by PIJ terrorists, after claims they were aid workersBollywood HungamaSCOOP: Ajay Devgn and Bhushan Kumar in talks for a big-budget spy thriller; looks at 2028 releaseZDF heuteAktuelle Pressemitteilungen des ZDFFootball ItaliaSerie A | Parma 1-5 Roma: Malen hero with four goals as big names returnANSA SportCalcio: Serie A, Parma-Roma 1-5NOSKlimaattop al een dag uitgelopen en onderhandelingen lijken muurvast te zittenGuardian SportIreland 20-17 South Africa: Nations Championship rugby union – live7sur7“Ma campagne était dans l’impasse”: François Ruffin retire sa candidature à la présidentielleBillboardGorillaz Celebrate Mexico’s ‘Revolutionary Spirit’ at Corona Capital, Bring Out Johnny Marr and TruenoANSAMorta la stilista Raffaella Curiel, 'l'intellettuale della moda'RTP DesportoCeltic goleia antes de visitar o TorreenseStraits Times SportLeeds bare their teeth to batter old foes Chelsea
The Daily Newsstand · Free, Always
Saturday, November 21, 2026

DPWH chief orders completion of Gandara Bridge by April 2027

Translate

TACLOBAN CITY, Philippines — Public Works Secretary Giovanni Lopez has warned the contractor of the Gandara Bridge Parallel Project in Gandara, Samar, against further delays, ordering it to strictly meet its April 2027 completion deadline following the collapse of two bridge girders during construction.

Lopez issued the directive during his inspection of the project along the Gandara diversion road on Friday, Nov. 20, three days after the two concrete girders fell while workers were installing them.

The incident, which occurred at around 7:30 a.m. on Nov. 17, did not result in any injuries.

Article continues after this advertisement

“The contractor has committed to maintaining the original timeline, which is 2027. We will not change that. If they need to work 24 hours a day, seven days a week, then they should do so,” Lopez told reporters.

FEATURED STORIES

NEWSINFO

NEWSINFO

NEWSINFO

He also warned that the department would not tolerate a repeat of the incident, stressing that the absence of casualties was the only fortunate aspect of the accident.

READ: Portion of P512-M bridge under construction in Samar collapses

“I do not want this incident to happen again. Fortunately, no workers were injured or killed. If something like this happens again, whether accidental or intentional, the consequences for those involved will be very serious,” he said.

Based on the project schedule, construction began on Dec. 17, 2024, with completion targeted for April 2027.

Article continues after this advertisement

Lopez clarified that the bridge project would be implemented in two phases, with a combined cost of more than P242 million, contrary to earlier reports that placed its cost at P512 million.

In a statement, contractor B. Vicencio Builders Inc. (BVBI) accepted responsibility for the collapse of the two prestressed concrete Type V girders, each measuring 35 meters long, and committed to shouldering the cost of their replacement.

Article continues after this advertisement

The contractor attributed the incident to the removal of a temporary support by two workers without the approval or supervision of project engineers.

According to BVBI, the two girders were initially positioned at around 6 p.m. on Nov. 16 as part of the installation of four girders that would support the bridge deck and carry traffic loads.

However, the installation was suspended because of time constraints and workers’ physical exhaustion, with the remaining two girders scheduled for installation the following day.

The contractor said one end of a partially installed girder was already resting on an elastomeric bearing pad, while the other end was temporarily supported by a roller.

Although project engineers had instructed workers not to disturb the temporary arrangement without their presence and approval, two workers allegedly removed the roller on their own.

This caused the partially positioned girder to lose its support and topple, striking the other girder and damaging both structures.

BVBI rejected suggestions that the incident resulted from poor workmanship, defective fabrication or substandard construction materials, maintaining that the collapse was caused by the unauthorized removal of the temporary support.

The company also assured the public that it would cover the materials and labor costs for replacing the damaged girders without additional expense to the government.

It further maintained that the bridge’s foundations, including its abutments and piers, were unaffected by the incident.

The DPWH has initiated an investigation into the collapse. Initial findings cited by Lopez pointed to human error, although the investigation is continuing.

READ: DPWH chief says human error caused Gandara Bridge collapse

DPWH 8 Regional Director Edgar Tabacon earlier said the department had started clearing the affected area and undertaking corrective measures, including the replacement of the damaged girders, to avoid further delays.

The incident has raised concerns over the safety and progress of the bridge project, which is expected to improve road connectivity in Gandara and nearby communities.

The original Gandara Bridge, constructed in 1968 along the Maharlika Highway, was closed in October 2020 after sustaining serious structural damage when an overloaded truck crossed it. Its closure forced motorists to use alternative routes, affecting transportation and accessibility in the municipality.

Your subscription could not be saved. Please try again.

Your subscription has been successful.

The parallel bridge project is intended to provide an alternative crossing and help address the long-standing transportation difficulties caused by the closure of the old bridge. /atm