Inquirer‘Mr. Pure Energy’ brings hope, music to kids in NegrosPunchSaraki condemns alleged intimidation of Kwara traditional rulersThe Jerusalem PostAfter Huang affair, NVIDIA's ex-sales head Puri found to have wed Super Micro executive - reportColliderNetflix’s New ‘Squid Game’ Replacement Officially Premieres in 1 MonthSouth China Morning PostCrafting a resilience blueprint amid polycrisis at Asian Insurance Forum 2026매일경제“화물 드론으로 태양광 설비를”…벤틀리, 크루공장 운영 탄소중립 검증سكاي نيوز عربيةترامب: نحاول منح إيران فرصة للتصرف بذكاءNew Straits Times3 RMAF officers, 3 civilians charged with drug traffickingEl ComercioSullana: Lluvia de gran intensidad provoca inundaciones en distintos sectores de la ciudad | VIDEOSNHKニュース【更新中】関文科相問責決議案 採決へ 可否は見通せない情勢The Hollywood ReporterMelissa Gilbert Expresses “Undying Gratitude” After Timothy Busfield’s Child Sex Abuse Case DismissedESPN DeportesRotondi analizó dejar Cruz Azul tras penal vs. América
The Daily Newsstand · Free, Always
Friday, November 27, 2026

You are reading The Indian Express on KioskNews: newspapers from many countries on one stand, each linked to its original. What other papers report

Up to 10 metres a night: How Mumbai’s Elphinstone bridge will cross rail tracks

Translate

With the last stretch of work on the soon-to-be reconstructed Elphinstone bridge underway, MahaRAIL, or the Maharashtra Rail Infrastructure Development Corporation Limited (MRIDC) is set to launch the structure’s girders from December 20.

Weighing 1,300 metric tons, 92 meters long, 11 meters high and placed on temporary structures seven meters tall, the gigantic open web girders will form the bones of the reconstructed Elphinstone bridge. The launch will be subject to whether approvals for railway blocks are given.

“The last stretches of work are ongoing,” said officials from the MRIDC tasked with completing the stretch of the reconstruction over the railway lines. “This includes the final works on the piers next to the railway tracks on which the bridges will stand, and the temporary trusses over them. The second girder is partly assembled, with more than half of the work on it complete.”

p to 10 metres a night: How Mumbai's Elphinstone bridge will cross rail tracks The 113-year-old Elphinstone Bridge at Prabhadevi is being redeveloped into a modern double-decker flyover, with 80 per cent of the reconstruction work completed in Mumbai. (Express photo by Akash Patil)

The reconstructed Elphinstone will be a double-decker bridge, with the bottom deck serving local traffic as a replacement of the old railway bridge. The top deck will be a part of the Sewri-Worli Connector, a 4.5 km connector connecting the Coastal Road at Worli to the Atal Setu at Sewri, which is being built by the MMRDA.

MMRDA officials announced that the bridge was 63% completed.

p to 10 metres a night: How Mumbai's Elphinstone bridge will cross rail tracks The reconstructed Elphinstone will be a double-decker bridge, with the bottom deck serving local traffic as a replacement of the old railway bridge. (Express photo by Akash Patil)

“The girders are being assembled in the day on top of the temporary arrangement built, using parts fabricated in Ghaziabad and then shipped here,” said an official. While the first web girder has been assembled, the second one, assembled behind the first, is around halfway done.

In response to a video circulating on social media that showed construction work continuing as commuters walked underneath it, officials said workers were equipped with all safety material and wear safety harnesses when working at a height.

p to 10 metres a night: How Mumbai's Elphinstone bridge will cross rail tracks MMRDA officials announced that the bridge was 63% completed. (Express photo by Akash Patil)

Once all preparations are in place, MRIDC will begin launching the girder. The official said, “A trolley system will be used to slowly slide the girder from the temporary structure over the railway tracks. Because the girder is currently at a height, it will go atop temporary trusses on the piers and temporary girders placed between the railway tracks. All this will be done in nightly corridor blocks of around 2 hours, pushing the girder around 8 to 10 meters every night.”

With a deadline of January in place to get the girders into place, MRIDC will begin road work on the lower and upper decks of the bridge. Once the girders are in place, this would free up space for J Kumar, the MMRDA’s contractor, to complete works on the portion of the bridge that leads up to the railway portion.

The latest deadline for the bridge’s reconstruction is May 31, 2027.

View the original on The Indian Express →