The Jerusalem PostTurkey denies Israeli claims, says no troops were at Syrian airbase struck by IDFESPN'Our window is not closed': Why Dan Campbell, other NFL coaches believe Lions will be back in 2026וואלהטורקיה: נמשיך לתמוך במאמצים של סוריה לפתח יכולות צבאיותDaily MaverickMotor racing-Verstappen commits to Red Bull until end of 2030Bollywood HungamaManoj Bajpayee to play Mahatma Gandhi in Sudhir Mishra directorial backed by Anubhav SinhaRTP DesportoMax Verstappen renova com a Red Bull até 2030 com o desejo de "voltar ao topo"PunchEx-Zambian minister killed during security raid – PoliceInquirer Entertainment‪Soft launch? Magui Ford gives glimpse of rumored romance with Robbie JaworskiSky TG24Guerra in Ucraina, Zelensky: "Russia investe su escalation, necessari mislli balistici Patriot"Wirtualna PolskaWygenerowali raport przez AI? W sieci lawina komentarzyVanguard‘I have been unfairly treated’ — Chidimma Adetshina laments deportation attemptEvening StandardLondon travel news LIVE: Major rail disruption through capital after person hit by train
The Daily Newsstand · Free, Always
Thursday, August 20, 2026

Lagos gets 360MW boost as FG upgrades four substations

Translate

The Federal Government (FG) has commissioned the upgraded transmission facilities in four major substations in Lagos, adding about 360 megawatts (MW) of transmission capacity to boost electricity supply across the state.

The projects at Ijora, Apapa Road, Alausa and Lekki substations are expected to strengthen bulk power delivery to residential, commercial and industrial consumers within the networks of Eko and Ikeja Electricity Distribution Companies.

Speaking during the commissioning of the projects, Minister of Power, Joseph Tegbe, said the investments were aimed at removing transmission bottlenecks and improving electricity reliability.

“These infrastructures have been here for over 25 years. What we are doing is commissioning new power transformers in Apapa, Ijora, Alausa and Lekki transmission substations. This is important as it will increase our wheeling capacity and also improve our delivery to end-users,” he said.

At Ijora, two new 100MVA transformers raised installed capacity from 90MVA to 230MVA, adding about 112MW, while the Apapa Road substation received two 60MVA transformers and modern gas-insulated switchgear, increasing capacity from 60MVA to 180MVA and adding about 96MW.

At Alausa, an existing 30MVA transformer was replaced with a 100MVA unit, raising total capacity from 135MVA to 205MVA and adding about 56MW. The additional capacity has increased power allocation to Ikeja Electricity Distribution Company to 80MW.

At Lekki, TCN commissioned two by 60MVA transformers, one by 300MVA transformer and nine additional 33kV feeders. The intervention doubled transformation capacity at the 132/33kV level from 120MVA to 240MVA.

Tegbe said the Alausa intervention alone could serve about 70,000 households, representing approximately 180,000 people, while the Lekki project would benefit about 100,000 customers, representing an estimated 400,000 people.

TCN Managing Director, Sule Ahmed Abdulaziz, said the projects were supported by the World Bank and JICA, with Shanghai Electric involved in execution.

View the original on Vanguard