PAC to begin Sabah Pan Borneo Highway probe next Wednesday

KUALA LUMPUR: The Public Accounts Committee (PAC) will begin its investigation into Phase 1 of the Pan Borneo Highway Sabah next Wednesday, starting with witnesses from the Works Ministry and the Sabah Public Works Department.
PAC chairman Datuk Wira Mas Ermieyati Samsudin said the committee would call those involved in managing and implementing the project, including officers who had served since it was first planned, to give evidence.
"The PAC will not compromise on any breach of financial procedures or elements of abuse of power, and will not let any responsible party escape accountability," she told a press conference at Parliament today.
The investigation follows findings on the project in the Auditor-General's Report Series 2/2026.
Mas Ermieyati said the committee held a 90-minute discussion yesterday with five Sabah member of parliaments.
They were Deputy Science, Technology and Innovation Minister Datuk Dr Mohammad Yusof Apdal (Lahad Datu), Datuk Seri Dr Ronald Kiandee (Beluran), Datuk Seri Wilfred Madius Tangau (Tuaran), Datuk Siti Aminah Aching (Beaufort) and Isnaraissah Munirah Majilis (Kota Belud).
"They shared first-hand accounts of conditions at construction sites, the daily problems faced by the people and the danger to road users' lives caused by delays to the project," she said.
She said the discussion gave the committee a better understanding of the problems.
Mas Ermieyati said the committee would refer any findings of misconduct for enforcement action.
The Sabah Public Accounts Committee has also been invited to participate throughout the investigation.
The toll-free Pan Borneo Highway was envisioned as a major transport link connecting Sabah, Sarawak and Brunei. However, progress in the two East Malaysian states has diverged sharply more than a decade after its launch.
The Auditor-General's Report Series 2/2026 found that 88 per cent of Phase 1 in Sabah, which spans 706km, remained incomplete after 11 years.
Only four of Sabah's 35 work packages had been completed. Of the remaining packages, nine were classified as sick projects, 13 were delayed and nine were ahead of schedule.
In contrast, Sarawak had completed 10 of its 11 work packages, with the remaining package, WP11, 99.9 per cent complete as at March 31.
Despite RM10.547 billion of the RM11.153 billion allocated for Sabah's highway project having been spent, it remains significantly behind schedule.
The completion deadline has since been extended to 2030 due to weaknesses in project planning.