JR Central announces delay in releasing maglev line’s opening schedule

Nagoya – Central Japan Railway (JR Central) will not be able to release an opening schedule by the end of this year for its planned Chuo Shinkansen high-speed magnetic levitation train line, President Shunsuke Niwa said.
“It has become difficult for us to announce (the opening schedule) within this year,” he said at a news conference on Wednesday. He cited delays in construction work and cost examinations.
Niwa said the company notified the transport ministry of the likely delay on Tuesday.
“We’d like to release the schedule as soon as possible after reviewing it,” he said.
JR Central has abandoned its original target of launching the maglev train service in 2027 due to delays in the start of construction on the section passing through Shizuoka Prefecture.
In July, Shizuoka Gov. Yasutomo Suzuki approved construction of the section, effectively ending a nearly nine-year impasse over the rail project. JR Central then said it would announce a new opening schedule within this year.
JR Central has estimated the total construction cost at ¥11 trillion, reflecting higher prices. However, the figure could rise even further as the opening date remains uncertain.