CNN TürkSabah namazı saat kaça kadar kılınır? Güneş doğduktan sonra sabah namazı kılınır mı?PunchMorning recap: Opposition challenges Tinubu, Daura emir faces sexual assault allegation, other top storiesBollywood HungamaREVEALED: Jio Studios backs Jaideep Ahlawat-Shefali Shah starrer Hisaab; 25 years after Aankhen, Vipul Shah promises a NEVER-BEFORE-SEEN bank heist drama in Indian cinemaInquirerDOTr to offer free rides in parts of NCR during 2-day transport strike한겨레서울 외곽·경기 남부 공시가 상승…강남 고가주택 보유세도 껑충ZDF heuteEntdecken Sie das ZDF-NachrichtenstudioSözcüNvidia CEO'su baştan çıkarttılar: Jensen Huang'ın sonu olan casusluk ağı ortaya çıktıSoompiBae Hyeon Seong, Cha Kang Yoon, And Park Yoon Ho Dish On Their Upcoming Drama “The Substitute”Observador DesportoEncosta de Manteigas pode demorar um ano a ser estabilizadaالشرقدراسة تكشف علاقة توزيع الدهون بتراكم بروتينات ألزهايمر في الدماغ7sur7Une fusillade éclate lors d’un concert en Californie: au moins 9 blessés, dont un graveGhaflaCreme De La Creme Opens Up About Four-Year Ordeal Before 2015 Video Leak
The Daily Newsstand · Free, Always
Monday, November 23, 2026

India’s 1st bullet train project hits milestone with Surat-Bilimora section energised

Translate

Mumbai-Ahmedabad bullet train corridor, India’s high-speed train project, achieves power milestone as 50-km Surat-Bilimora section is energised; Surat-Vapi operations deadline now stands at late 2027

The ministry has recently pushed back the target for launching Bullet Train services on the 100-km Surat-Vapi stretch. (Image for representative purpose only)

Mumbai-Ahmedabad bullet train corridor: India’s first bullet train corridor has achieved yet another milestone. The overhead electrical equipment that will supply power to trains on the Surat-Bilimora stretch of the 508-km Mumbai-Ahmedabad Bullet Train corridor has been successfully energised, the railway ministry announced on Saturday.The process will now move ahead in phases, with shorter stretches being energised one at a time.The Surat-Bilimora stretch covers around 50 km between the two stations, with the tracks running along an elevated viaduct. The route crosses four rivers by means of bridges and also includes a steel bridge spanning National Highway 53.The Surat-Vapi corridor is the first stretch of the bullet train or high-speed rail corridor that is expected to be operationalised in the second half of 2027.

‘Energisation’ of India’s first bullet train corridor

"Energisation will be carried out progressively in smaller sections, under the close supervision of technical teams to ensure safety and compliance with prescribed procedures," a railway ministry press statement said.Alongside the development, the ministry issued a public safety warning asking residents, commuters, construction personnel and others in areas near the corridor to stay away from overhead electrical equipment.

It also cautioned against touching these installations or carrying out any unauthorised activity near the section.Officials clarified that switching on the power supply does not indicate that the stretch is ready for passenger train services. However, they described the milestone as an important step towards making the section operational.The ministry has recently pushed back the target for launching Bullet Train services on the 100-km Surat-Vapi stretch.

The deadline, initially set for August 2027, has been moved to the final quarter of 2027."The section comprises both Up and Down lines on the elevated alignment and marks an important advancement towards further testing activities for the project," the ministry said.The ministry said the Mumbai-Ahmedabad Bullet Train corridor uses an advanced 2 × 25 kV overhead traction system, a sophisticated electrification technology deployed in high-speed rail networks around the world.Power for the system will be drawn from the national grid through 14 traction substations (TSS) positioned at strategic points along the 508-km route. "The electrification network comprises 14 strategically located traction substations (TSS) along the 508-km corridor. These substations will receive power from the national grid and supply it to the overhead traction system used by high-speed trains," the ministry said.

A centralised control centre will oversee the entire electrical network, enabling the system to be monitored for safe and dependable operation.To reduce noise reaching nearby areas, the viaduct has been fitted with around 94,000 noise barriers, officials said.

View the original on Times of India →