PunchPolice confirm 30 killed in Niger reprisal attackCNN TürkEmre Belözoğlu, Şampiyonlar Ligi'nde Fenerbahçe tarihine geçtiThe Jerusalem PostNorth Korea's Kim calls for wider deployment of tactical nuclear weapons매일경제더불어민주당 정책조정회의 입장하는 한병도 원내대표The Sydney Morning HeraldMonaco will have a starring role in 2027New Straits TimesVietnam working with US to complete trade deal soonCollider10 Unwatchable Movies That Were Pure Cash GrabsThe Indian ExpressThe data centre trap — big investments, few jobs and little domestic valueLa NaciónRené Descartes, filósofo, sobre la duda y la existencia: “Si pienso, tengo que estar existiendo”CBS NewsMacy's Thanksgiving Day Parade postponed for 1st time in historyInfobaeMario Duarte vuelve a la carga con La Derecha y un tema con videoclip protagonizado por Zharick LeónEl ComercioResultados Quini 6, 25 de noviembre: los números del sorteo 3429 por $7.500 millones
The Daily Newsstand · Free, Always
Thursday, November 26, 2026

Power supply curtailed in parts of Kumasi as illegal logging damages GRIDCo line

Translate

Power supply to parts of the Western and Ashanti regions has been disrupted after illegal chainsaw operators felled a large tree onto a major 330kV transmission line operated by the Ghana Grid Company Limited (GRIDCo).

In a statement issued on Wednesday, November 25, 2026, GRIDCo said the 330kV transmission line running from Aboadze to Anwomaso tripped in the late afternoon, interrupting electricity supply.

Following the trip, GRIDCo engineers patrolled the affected corridor and carried out investigations, which established that a large tree cut down by chainsaw operators had fallen onto the line and caused damage.

Because of the unavailability of the critical transmission line, system operators have had to scale back power supplied to parts of Kumasi.

GRIDCo stated that its engineers are working diligently to carry out repairs and restore the damaged line as quickly as possible.

The company apologised to affected consumers for the inconvenience and assured the public that normal supply would resume once repair works are completed.

Add MyJoyOnline as a preferred source on GoogleSee more of our stories when you search on Google. (opens in a new tab)

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.

Tags:  

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.

View the original on MyJoyOnline →

KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.