PunchMorning recap: FG announces 19 international job vacancies, Jimmy Odukoya sues sister, seven others, other top storiesThe Jerusalem PostOver two-thirds of wounded soldiers returned to combat since start of war, IDF saysNU.nlVerstappen boekt in spectaculaire GP van Las Vegas vierde zege van het jaarEl ComercioEl Perú que necesitamos: el mensaje del papa León XIVCapital FMKenyans in Diaspora offer Sifuna billions to build JKIA if he wins the presidencyZDF heuteEntdecken Sie das ZDF-Nachrichtenstudio매일경제조국, 혁신당 ‘당명 개정’ 제안…“이름 겹쳐 일부 조롱…확장성 있는 이름 필요”ColliderThe Masterpiece Heist Thriller That Inspired Michael B. Jordan’s New Film Officially Hits Free StreamingDaily MailHonorary Cyrus! Elizabeth Hurley joins family photos at Miley's wedding as boyfriend Billy Ray's date along with son Damian… amid engagement rumorsGMA NewsLOOK: Sara Duterte prays for peace, safety during Catbalogan church visitn-tvNeurologen-Kritik wegen Musiala: Nach Rummenigge-Knall: Bosse des FC Bayern erklären sichLenta.ruВ США объяснили отказ передать Украине управление Starshield страхом перед Россией
The Daily Newsstand · Free, Always
Sunday, November 22, 2026

Visayas grid under yellow alert on Sunday, Nov. 22, 2026 - NGCP

Translate

Make this your preferred source to get more updates from this publisher on Google.

A declaration of yellow alert status over the Visayas grid is expected on Sunday, November 22 due to tight energy reserves, the National Grid Corporation of the Philippines (NGCP) said.

In an advisory, the yellow alert status will take place between 5 p.m. to 9 p.m.

The grid is currently running on an available capacity of 2,380 megawatts (MW) although the peak demand is 2,347 MW.

The yellow alert status declaration is due to the unavailability of several coal plants in the Visayas region.

There will be unplanned outages of Therma Visayas Inc. 2 and Palinpinon I Geothermal Power Plant Unit 1.

Meanwhile, there are planned outages on Palm Concepcion Power Corporation and KEPCO SPC Power Corporation Unit 2.

Further, the NGCP said that there is a limited transfer capacity of Mindanao-Visayas interconnection due to scheduled maintenance of Baloi-Kauswagan 230kV Line 1.

Meanwhile, eight plants are on forced outage in November, one plant since October, two plants since September, two plants since August, one plant since June, three plants since 2025, one plant since 2024, two plants since 2023, and one plant since 2021. There are also 21 plants running on derated capacities, for a total of 668.4MW unavailable to the grid.

A yellow alert is issued when the operating margin is insufficient to meet the transmission grid’s contingency requirement.

To address the thinning energy reserves in the Visayas grid, the Department of Energy (DOE) earlier ordered the NGCP to install over 250 megawatts of battery energy storage system.

The Energy Regulatory Commission (ERC) also earlier issued 24 show-cause orders (SCO) against 13 power generation companies over power outages that hit the Visayas and Mindanao. —Vince Angelo Ferreras/RF, GMA News