PunchVIDEO: Putin’s nuclear briefcase caught on camera in ChinaThe Jerusalem PostKahana must bring unity to Knesset through careful, patient action, not charging ahead - editorialInquirer Entertainment‘PBB’ housemate Calix Esguerra enjoys support of fellow pageant kingsInquirerCHR probes alleged rights violations in mass arrest of Asean protesters한겨레부전∼마산 복선전철 터널 붕괴 원인은 “허용치 20배 넘는 주입 압력”ZDF heuteEntdecken Sie das ZDF-NachrichtenstudioComplete SportsFIFA Unveils NFF Normalisation CommitteeHet Laatste Nieuws“Het wachten meer dan waard”: ook BV’s vieren de release van langverwachte game ‘GTA VI’RapplerAs Meta bets big on Muse AI agent, early safety mishaps surfaceThe Sydney Morning HeraldAustralian cricket’s reputation on the brink of being reduced to ashesNDTVStock Market Today: Green Energy Stock In Focus After Rs 12.98 Crore Windfall. Should You Buy?TagesschauLiveblog zum APEC-Gipfel: ++ Trump und Putin beenden ihr Gespräch ++
The Daily Newsstand · Free, Always
Thursday, November 19, 2026

三峡枢纽新通道首条500千伏线路完成迁改

Translate

  中新网宜昌11月19日电 (郭晓莹 孙钰芳 孙小敏)据三峡集团19日消息,首条穿越三峡枢纽新通道上方的三江Ⅱ/Ⅲ回500千伏输电线路完成迁改,为后续航道开挖施工腾出了空间。

三峡枢纽新通道先行开挖区旁新建的500千伏线路铁塔。(资料图)何伟 摄

  三峡枢纽新通道是三峡水运新通道工程的组成部分,位于已建三峡船闸北侧,规划新建双线连续五级船闸。三江Ⅱ/Ⅲ回500千伏原输电走廊位于三峡枢纽新通道上游引航道范围内,需进行整体迁改。为确保施工期间“航道施工不停、水电外送不断”,国网湖北超高压公司采用“先建后拆、负荷转移”的方式,先建成新走廊线路并将负荷平稳转移,再拆除旧塔,为航道开挖创造条件。

国网湖北超高压公司作业人员在三江Ⅱ/Ⅲ回500千伏线路迁改工程A6号铁塔挂设放线滑车,为导线展放做好准备。何伟 摄

  此次线路迁改跨越三峡枢纽新通道先行开挖区,该区域于今年9月完成全部爆破作业。“线路迁改完成后,待新线路通电、原有线路及铁塔拆除,原线路占压区域即可全面启动爆破开挖,进一步推进航道施工。”国网湖北超高压公司宜昌运维分部施工项目总工李淅涛表示。

  三江线起于三峡电站,止于江陵换流站,长约135公里。三江线与三龙线(三峡至龙泉换流站)等线路共同构成三峡电力外送的核心交流骨干,将三峡发出的电力汇集至换流站,再转换为直流电向华东、华南等负荷中心远距离输送。三峡水运新通道工程建设涉及的迁改线路共52条,其中500千伏主干线路8条。(完)