Track replacement work will delay services at 3 LRT stations on Sunday
KUALA LUMPUR: Track replacement work on the Kelana Jaya LRT line on Sunday will involve Kerinchi, Abdullah Hukum and Universiti stations.
Rapid KL said in a statement train services at the affected stations would begin at 9.30am.
Free shuttle buses will operate from 6.30am to 9.30am, connecting Taman Jaya, Universiti, Kerinchi, Abdullah Hukum and Bangsar stations.
The buses will run every five to 10 minutes.
Rapid KL is carrying out track replacement work on the Kelana Jaya line in seven phases, from Sept 13 to September 2027.
The work is aimed at ensuring the tracks remain safe and reliable.
Stations affected by the work will open at 9.30am instead of the usual 6am, while unaffected stations will operate as usual.
The first phase involved Gombak and Taman Melati stations on Sept 13, 20 and 27, followed by the second phase involving Universiti, Kerinchi and Abdullah Hukum stations on Nov 15, 22 and 29.
The third phase will cover Dato' Keramat, Jelatek and Setiawangsa stations on Jan 10, 17 and 24, 2027.
The fourth phase will involve Universiti, Kerinchi and Abdullah Hukum stations on March 14, 21 and 28, next year, while the fifth phase will cover Masjid Jamek, Dang Wangi, Kampung Baru, KLCC and Ampang Park stations on May 9, 16 and 23, next year.