ESPN DeportesJalen Duren, pívot de los Pistons, estará de baja al menos dos semanas por una distensión en los isquiotibialesESPNFollow live: Chiefs get on the board; Seahawks hold controlPunchPolice arrest school driver for kidnapping, raping Delta studentThe Jerusalem PostFor many Israeli voters, concerns over Israel's public image take a back seat in election한겨레한국 재즈 100년의 항해…31일 한강서 ‘물빛 재즈 크루즈’Daily MaverickLula, Brazil’s iconic working class president, wins historic fourth term in dramatic comebackZDF heuteEntdecken Sie das ZDF-NachrichtenstudioSBS 뉴스[자막뉴스] 10년 넘어 부활 '특별감찰관'…"눈 부릅뜨고 감찰하겠다"Capital FMPresident Ruto Dismisses Election Results Livestreaming Ban Claims as PropagandaCNN TürkOtomobil, yol yapımı için kazılan çukura düştü; 1 ölü, 5 yaralıNew Straits TimesPenang landslide: Resident returns to feed her dogSRF NewsStichwahl ums Präsidentenamt – Amtsinhaber Lula da Silva in Brasilien wiedergewählt
The Daily Newsstand · Free, Always
Monday, October 26, 2026

NGCP: Visayas grid under yellow alert on Monday, Oct. 26, 2026

Translate

Make this your preferred source to get more updates from this publisher on Google.

The Visayas power grid will be placed under yellow alert on Monday due to thin reserves resulting from the unavailability of several power plants.

In an advisory, the National Grid Corporation of the Philippines (NGCP) said the yellow alert will be hoisted over the island cluster from 5 p.m. to 6 p.m.

The grid operator said the Visayas grid is currently operating at 2,689 megawatts (MW) capacity against a peak demand of 2,473 MW.

The NGCP cited the following factors that contributed to the yellow alert declaration in the Visayas grid:

  • Unavailability of Visayas’ large coal plants TVI 1 and KSPC 1
  • Limited power import from the Mindanao grid due to the unavailability (planned outage) of GNPK 4 and TSI 2.

It added that 12 plants are on forced outage in October, two plants since September, two plants since August, one plant since June, three plants since May, three plants since 2025, one plant since 2024, two plants since 2023, and one plant since 2021, while 16 plants are running on derated capacity.

The outages and derated capacities of dozens of plants resulted in a total of 650.3 MW unavailable to the Visayas grid.

A yellow alert is issued when the operating margin is insufficient to meet the transmission grid’s contingency requirement.

While supply is still enough to meet current demand, it no longer reaches the required safety margin. —AOL, GMA News