PunchMan United defender Martínez blames club hierarchy after Atlético defeatCNN TürkPolonya’yı Sarsan Casusluk: Veriler İsrail’e mi Aktarıldı?The Jerusalem PostNetanyahu denies ever having met Egypt's foreign intelligence chief despite contradictory recordsInquirerNIA completes 170 solar-powered irrigation projects in CalabarzonBollywood HungamaKhosla Ka Ghosla 2 release postponed to March 5, 2027Daily MaverickBOOK EXCERPT: Kitchens of the Karoo – how cooks of old mastered stone, sourdough and coffeeESPNTakeaways as Rays even series against Guardians한겨레청주시 수도권 쓰레기는 차단 ‘성공’…다른 지역 쓰레기 유입은 ‘글쎄’Inquirer EntertainmentFormer ‘RuPaul’s Drag Race’ music producer Lucian Piane dies in road accidentZDF heuteEntdecken Sie das ZDF-NachrichtenstudioBillboardCezary Skubiszewski to Be Saluted at 2026 Screen Music Awards20 MinutenSchweizer (73) kehrt wegen Handy um – und verschwindet spurlos
The Daily Newsstand · Free, Always
Wednesday, October 14, 2026

謝國樑:基隆捷運朝雙軌進行 第2階段路線不廢除鐵路

Translate

行政院公共工程委員會正式通過基隆捷運工程經費審議,總經費696.89億元,中央負擔519.98億元,其餘由北北基分擔。負責推動的新北市政府捷運工程局也宣布,基隆捷運機電系統及軌道統包工程正式決標。針對基隆捷運第2階段路線,市長謝國樑表態「絕對不可廢除鐵路來替換捷運」。

斜坡上搭起圍籬,基隆捷運百福站出入口預定地先期工程已經展開,基隆捷運計畫總經費696.89億元通過行政院審議,其中,中央負擔519.98億元、台北市分攤57.54億元、新北市71.44億元、基隆市政府負擔47.92億元,資金到位,力拼2033年完工。

當地居民表示,「當然有幫助,坐車方便,我們老人是這樣想的。」

當地居民說:「蓋在我家旁邊,捷運站是對我們比較有利,不然我們要走去百福車站也是可以搭車。」

基隆捷運第1階段將在基隆境內設置5站,由堵南街往五福橋、六合橋,一路延伸至台鐵八堵站。配合經費審查通過,原採保留決標的機電與軌道統包工程依程序正式決標,確定與汐東線、民汐線採用一致的機電系統。

基隆市交通處副處長黃詩涵說明,「未來的基隆捷運將會跟汐東線、民汐線採用一致的機電系統,那通車之後民眾就可以從基隆的八堵一車到底,免換車直接到達台北大稻埕。」

而負責興建基隆捷運的新北市捷運局,工程人員已經進駐沿線據點,全線車輛、號誌等核心系統,順利銜接汐東線將是關鍵。

新北捷運工程局副發言人陳儀蓉表示,「機電系統能夠順利的來決標,最快年底就能開工,朝2033年完工的目標持續來邁進。」

基隆市長謝國樑則強調,經費核定後基隆捷運將朝「雙軌」進行,一軌是捷運建設,一軌是都市發展,至於第2階段路線會朝「不廢台鐵」方向來推動。