The Jerusalem PostMossad kidnapped Iranian official, dumped body in Black Sea while searching for Ron Arad - reportPunchGuinea expels 1,557 foreigners over illegal gold miningInquirer EntertainmentKatrina Anne Johnson fuses PH, Japan looks in Miss International 2026 costumeInquirerTransCo to Mindoro consumers: Avoid unnecessary power consumptionDaily MaverickMadlanga Commission: ‘Take the money, and let suspects go’ — JMPD officer details alleged police interference한겨레김민석, ‘발언 논란’ 최민희 징계 속도…중징계 땐 친명·친청 전면전ZDF heuteEntdecken Sie das ZDF-Nachrichtenstudio3DNewsКитайский электросамолёт CE-25A выполнил первый испытательный полёт с людьми на бортуComplete Sports2027 U-23 AFCONQ: Daga Out Of Nigeria vs DR Congo Second Leg TieRadio-CanadaRencontre Carney-PSPP au Cambodge : « Ça s’est bien passé, c’était sympathique »La TerceraIncendian casa de periodista panameño tras ataque con explosivosIl Fatto QuotidianoUcraina, Cremlino: “Se non ci sarà un accordo politico con l’Europa useremo la forza”
The Daily Newsstand · Free, Always
Sunday, November 15, 2026

London’s data centre boom ‘could push 10,000 households into poverty’, Sadiq Khan warned

Translate

WEST END FINAL

London’s data centre boom could push 10,000 households into fuel poverty and place unprecedented strain on water resources, experts have warned.

They are disproportionately placed in and around London due to their proximity to the financial hub in the City of London, as well as the “snowball effect”, where new data centres are built near existing ones in “clusters”.

Oliver Hayes, head of campaigns at Global Action Plan, has warned that high-growth data centre projections could force 77,000 British households into fuel poverty in future – including 10,000 in the capital – due to increased energy bills.

What as planned data centre at Charlton Riverside would like like

What a planned data centre at Charlton Riverside would like like

GLi

Research from the climate campaign group reveals that added demand on the UK’s energy systems from new data centres could add an average of £88 to the average household energy bill.

“It will also further impoverish the households already in fuel poverty,” Mr Hayes told the London Assembly Environment Committee last week.

“This is an enormous issue that is not being adequately considered. Early analysis of that at a regional level suggests that in London that figure would be about 10,000 additional households.”

Zack Polanski, the leader of the Green Party and London Assembly Member who sits on the committee, told the Local Democracy Reporting Service (LDRS): “We need to slam the brakes on the rampant building of new data centres.

Protesters hold placards outside the Department of Energy Security and Net Zero calling for a stop to the expansion of large-scale data centres, on November 6, 2026

AFP/Getty

“So many Londoners are already struggling with the toxic combination of sky-high bills and low wages.

“Building more data centres risks pushing tens of thousands more households into fuel poverty, and that’s especially worrying here in London, where so many data centres are being proposed.

“Data centres don’t just threaten our climate targets by driving up emissions, but at a time when London is facing a housing emergency we cannot afford to prioritise data centres ahead of the homes our city desperately needs.”

The structures will also consume huge amounts of water, Assembly Members were told, which could lead to significant issues during “peak demand” in summer.

Jon Chappell, deputy director of Water UK, said: “We build our system to meet the highest point of demand in the year.

Bridge Road data centre in Southall

Ealing Council has given the go-ahead for a data centre at Bridge Road in Southall

Ealing Council

“If you have a big extra new demand in summer, that increases the peak. That means you have to increase the size of your service reservoirs and your treatment works.”

If every data centre to come was built like the least efficient one currently in existence, he claimed the country would need an extra 77million litres of water a day – the equivalent to three London boroughs.

This could have a knock on effect on other parts of ministerial and City Hall’s ambition, Mr Chappell suggested, adding: “We are in a position where in the east of England and in the southeast of England, there are places where houses cannot be built and businesses cannot expand already for no other reason than a lack of water.”

Oliver Hayes, head of campaigns at Global Action Plan, has warned that high-growth data centre projections could force 77,000 British households into fuel poverty in future – including 10,000 in the capital

London Assembly

Researchers also warned the cross-party committee that headline figures around water only captures a fraction of the true cost.

Rory Murphy, a Research Associate at the University of Exeter, noted that while US data centres used 66billion litres of water directly to cool servers in a given year, 800billion litres was used to keep the servers on in the first place.

“We need to consider the wider indirect effects, particularly when considering the stress that this could place on an already stressed infrastructure,” he urged.

The Mayor of London, when asked about this concern last year by Labour Assembly Member James Small-Edwards, said he had commissioned a study on the implications of new data centres on the capital’s water supply, adding: “Data centres use a variety of cooling technologies, with some requiring water while others use air cooling or non-water systems. The impact of data centres on water infrastructure and supply can therefore vary considerably.”

Earlier this year, he told Assembly Members: “We are looking at what we can do in terms of the water impact and what we can do in terms of the grid impact and of data centres.

“We are looking into the issue of the impacts on demand for water, the domestic demand for water, particularly in hot summer times if people are increasingly using AI. Again, my point about the offsetting in terms of what is not being done because of the energy and water required by data centres is really important. That is why we need a proper comprehensive plan for London.”

The draft London Plan, which guides councils on planning, says data centres in suitable locations should be supported in principle, but should only be given the go-ahead if water and electricity capacity is available.