The Jerusalem PostPentagon ignored warnings before Iranian drone strike killed six US soldiers, whistleblower allegesInquirer EntertainmentBianca Gonzalez shares how PBB prepares evictees for outside lifeInquirerAnnual 3-month sardine fishing ban starts in Zamboanga PeninsulaDaily MaverickANC cannot renew itself by looking inwards while voters turn awayZDF heuteEntdecken Sie das ZDF-NachrichtenstudioVilaWebLa CUP aposta pel conflicte amb l’estat espanyol com a via d’avenç socialRTL BoulevardACM: Investeerder HAL mag bouwbedrijf VolkerWessels overnemenSRF NewsGlobale Panne – Alter Programmfehler löste Microsoft-Ausfall ausEgypt IndependentTV host Amr Adib comments on Egyptian state selling lands to pay off debtABC NewsWATCH: New video of tanker collision and riverboat sinkingTechCrunchGoogle Maps can now build trip itineraries with real-time details about each stopVanguardASUP declares indefinite strike at Rivers polytechnic
The Daily Newsstand · Free, Always
Monday, November 16, 2026

Millions spent, years wasted: Israeli tourism projects face severe delays amid oversight failures

Translate

Government tourism projects have taken years to complete while the bodies responsible for overseeing them lacked a comprehensive picture of whether they were being delivered efficiently, according to a State Comptroller’s Office report published on Monday.

The audit found that the Tourism Ministry, the Government Companies Authority, and three state-owned companies managing tourism infrastructure lacked the information needed to assess performance across projects, including whether they met deadlines and budgets and the quality of the work.

The government’s plan to consolidate those activities was itself based on incomplete preparatory work, the report found. Officials examined potential savings from a merger but did not assess the companies’ performance or whether other ways of managing projects would work better.

The companies oversee public tourism infrastructure - including promenades, parks, historic and religious sites, and urban tourist routes. They manage planning and hire contractors and supervise construction; meaning, they don’t carry out the building work themselves. Their combined annual activity amounted to hundreds of millions of shekels in 2022-2025.

The audit examined the Israel Government Tourist Corporation, the Dead Sea Preservation Government Company, and the Old Akko and Nazareth Development Company. It covered 68 projects carried out between 2010 and 2025, with expenditure totaling approximately NIS 377 million.

People enjoy the warm, sunny weather at a beach along the Dead Sea, November 13, 2026.
People enjoy the warm, sunny weather at a beach along the Dead Sea, November 13, 2026. (credit: Rachel Alroey/Flash90)

Without a consolidated record to work from, the comptroller’s office built its own database to examine project timelines and budgets.

At the Government Tourism Company, contractors took at least twice the allotted time in 22 of the 30 projects examined for which a completion deadline had been set. In three, the work took at least nine times as long as planned.

Delays also occurred before construction began. In 12 of 46 projects examined, at least five years passed between receipt of a work order and the signing of an agreement with the local authority. In two, that stage alone took at least a decade.

All nine projects examined at the Akko and Nazareth company exceeded their contractors’ allotted construction time, as did all six Dead Sea company projects examined for which such deadlines had been set.

Government, Dead Sea tourism companies failed to monitor budgets

Budget monitoring was also deficient. The Government Tourism Company did not analyze spending against original project budgets and did not treat supplementary funding for unforeseen events as an overrun of those original budgets. The Dead Sea company likewise did not conduct that comparison, and its information system did not distinguish original allocations from later additions.

Administrative spending was substantially higher than at comparable government companies. In 2025, management and general expenses accounted for 10.5% of total expenditure at the Akko and Nazareth company, 11.1% at the Government Tourism Company, and 12.8% at the Dead Sea company, compared with an average of 4.8% at other government project-management companies.

The audit also found failures in basic corporate oversight. As of September 2025, the Dead Sea and Akko and Nazareth companies had each operated with only one board director for approximately four years, leaving them without enough directors to hold valid board meetings. They had also lacked audit committees for approximately five and six years, respectively.

The report identified ministers’ failure to appoint directors as a principal cause of the governance deficiencies.

In January 2026, after the main audit period, the government approved merging the Akko and Nazareth company into the Government Tourism Company and transferring the Dead Sea company’s tourism-development activity to it.

But the team preparing the plan examined savings on salaries, services and suppliers without assessing project delivery or work quality, the audit found. It also did not evaluate alternatives such as contracting directly with private project managers, even though the Government Tourism Company had already outsourced management of roughly 42% of its projects, wholly or partly, in 2022-2025.

Some steps toward stronger oversight were recorded. The Government Companies Authority set efficiency targets for the Dead Sea company in 2025 and the Government Tourism Company in 2026. During the audit, the Tourism Ministry introduced measures for counting completed projects and those moving from planning to construction, but did not set numerical targets against which success could be judged.

The comptroller’s office called for better information systems, stronger oversight and completion of board appointments. It also found that an earlier recommendation remained unfulfilled: agreements requiring municipalities to maintain completed tourism sites still lacked agreed sanctions or enforcement measures for breaches.

State comptroller tourism report completed before Englman's term ending

The main examination ran from November 2024 to September 2025, with supplementary checks through June 2026.

The report had already been completed and submitted to the prime minister and the State Control Committee chairman in early July, before Matanyahu Englman ended his term as state comptroller. According to the comptroller’s office, the dissolution of the previous Knesset prevented it from being tabled and published after the statutory 10-week interval. The new Knesset’s swearing-in has now allowed its release.

Israel has remained without a comptroller since July, after the High Court invalidated attorney Michael Rabello’s election because ballot secrecy had been violated. Earlier this month, the court found that Knesset Speaker Amir Ohana had breached its ruling by failing to arrange a repeat vote, but left the appointment to the incoming Knesset. Rabello subsequently withdrew his candidacy.

Comptroller’s Office staff can continue existing audit work and investigate public complaints, but cannot exercise powers reserved for the comptroller, including finalizing new reports, launching new audits or issuing protection orders for whistleblowers. The tourism report had already been completed under Englman before the vacancy began.

View the original on The Jerusalem Post →