InquirerProsec agrees: Hard to explain VP Duterte funds even with lumped SALNESPN DeportesAsí vivimos jornada 3 de Series Divisionales de Liga NacionalThe Jerusalem PostThree years later, October 7 is still not in the past for Israelis - editorialESPNPadres survive Brewers in Game 3 to extend series한겨레‘산후조리비 지원’ 오락가락 행정…혼선만 부추기는 경기도ZDF heuteAktuelle Pressemitteilungen des ZDF20 MinutenWas hinter der Wut von Frankreichs Jugendlichen stecktCNN TürkAbdulkadir Selvi yazdı... Fon soruşturmasında mesaj net "Çürüyen kol kesilip, atılır"UOLIncêndio atinge fábrica de velas no Jabaquara e teto desabaالنهاراستثمارات كوشنر تحت تدقيق الكونغرس... ما علاقة شركة إسرائيلية بالملف؟SoompiYoo Yeon Seok Is A Single Dad Who Faces Unexpected Crisis In New Drama “The Perfect Lie”01netQualcomm et ARM s’étrillent à nouveau devant la justice : le prix de votre prochain smartphone va-t-il augmenter ?
The Daily Newsstand · Free, Always
Wednesday, October 7, 2026

AG's report: Khaled to address LCS project issues in Parliament today

Translate

HULU SELANGOR: Defence Minister Datuk Seri Mohamed Khaled Nordin will address issues concerning the navy's Littoral Combat Ship (LCS) project in Parliament today.

"If it is regarding the LCS issue, yes, I will be going to Parliament today to answer them this afternoon," he said when met after a working visit to local defence firm High Point Worldwide Sdn Bhd here today.

On Monday, the Auditor-General's Report 2/2026 found that the LCS project was 7.55 per cent behind schedule as of June 25, putting the physical handover of LCS 1 at risk.

This was due to the Naval Strike Missile Launcher System remaining outstanding following the permanent cancellation of its export permit by the Norwegian government.

The Defence Ministry, in response to the report, said LCS 1 would not be able to operate at full capability without the system installed, although it could consider a conditional handover while the contractor remained contractually obligated to install and integrate it.

Auditor-General Datuk Seri Wan Suraya Wan Mohd Radzi said the delay of between 30 and 108 days could affect the earliest scheduled handover on Aug 26, or the revised target of Dec 26.

She said LCS 1 would not achieve full capability if handed over before its training and weapons systems were completed, while delays to the first ship would also affect the handover schedules for LCS 2 to LCS 5.