News24 | Busisiwe Mavuso | The grid is choking SA, and the fix keeps slipping

Translate

South Africa’s programme to attract private investment into building new electricity transmission lines has been delayed from the third quarter of this year to the second quarter of next year — a setback for the country’s economic growth targets, which depend on expanding the grid to unlock more power generation.

South Africa’s programme to attract private investment into building new electricity transmission lines has been delayed from the third quarter of this year to the second quarter of next year — a setback for the country’s economic growth targets, which depend on expanding the grid to unlock more power generation.

Getty Images

The timetable for the crucial expansion of SA’s grid infrastructure has suffered an unfortunate slippage, writes Busiswe Mavuso.

The Independent Transmission Projects (ITP) Programme is set to mobilise substantial private investment into building out South Africa’s electrical grid infrastructure.

It is critical to the country’s economic growth targets as it will unlock greater electricity generation and access. But an announcement earlier this month from the Department of Electricity and Energy (DEE) and National Treasury has delayed the request for proposals from the third quarter of this year to the second quarter of next year – and that is an unfortunate slippage of the timetable.

READ | SA’s massive power grid expansion plan delayed by 6 months

The good news is that there has been real institutional capacity building to support the process. A delay is better than rushing to market with a call for proposals that can’t be properly managed or lead to excessive pricing because bidders can’t assess the risks. A failed procurement would lead to more delays and be more expensive than a pause while government gets it right.

One important intervention is the creation of a credit guarantee vehicle that will protect investors from credit risks stemming from the National Transmission Company South Africa (NTCSA).

That vehicle is being created by National Treasury, the World Bank, FSD Africa and the Development Bank of Southern Africa.

The NTCSA is in the process of being unbundled from Eskom, together with its transmission assets. Once done, it will form the Independent Transmission System and Market Operator (ITSMO), which will be the counterparty to investors building out grid infrastructure. It will be the first time private investors have the opportunity to invest in transmission lines in South Africa.

Given that the ITSMO is still in the process of being established, bidders would face a counterparty that does not yet have its own balance sheet or credit history. So, the guarantee vehicle provides an important risk management function that will ensure bidders have the confidence to make long-term, multibillion-rand investments.

The guarantee vehicle was incorporated in August and is now being geared up to be able to support the programme.

But the timelines are a concern.

Wanted: Clear timetable

On the current trajectory, the new grid infrastructure is unlikely to be in operation by the end of the decade. While the announcement targets a request for proposals in the second quarter, it made no commitment to the timings thereafter, which will need to include bid adjudication and negotiation with the winners before getting to financial close, when construction can actually begin. A clear timetable for that whole process now would help manage expectations and enable planning.

The grid is already the binding constraint for new electricity generation, as we currently cannot get electricity from where it is cheap to generate to where it needs to be consumed.

Eskom and Business Leadership South Africa are aligned on concluding the establishment of the ITSMO, with Eskom’s transmission assets unbundled to it. Swiftly finalising that process will help build confidence in the whole grid investment outlook, as investors will then know exactly what they are dealing with.

The ITSMO will be the buyer of grid capacity from investors, so its own creditworthiness will be important in the risk outlook. The guarantee vehicle will help, but having a robust institutional buyer underpinning it will provide additional confidence.

The first phase of grid investment calls for only 1 164km of new lines even though the NTCSA’s plan is to have 14 500km by 2034. So this procurement needs to be swiftly followed by others.

I welcome the DEE and National Treasury’s commitment to the process and the institutional development that has occurred. It would build confidence if SA had a complete timetable through to financial close and for associated reforms such as the SA Wholesale Electricity Market, which has also been subject to deadline slippage and is key to facilitating competition in the electricity sector.

Business will play a fundamental role. Banks and fund managers will be critical investors in grid infrastructure, and we are supporting Eskom and other key players to conclude the restructuring process.

Of course, none of this is for its own sake – electricity reliability and competitive prices are growth enablers; they allow businesses to invest and expand, ultimately creating the jobs our country desperately needs. Sticking to reform timetables will help us reach that destination sooner.

A nod to Nobel Peace Prize winner Navi Pillay

My congratulations to Navi Pillay on winning the Nobel Peace Prize last week. She is South Africa’s fifth Peace Prize winner and an example to the world of professionalism and a commitment to justice and human rights.

The prize is a reminder of the important role South Africans have played in international institutions and in developing human rights jurisprudence.

Busisiwe Mavuso is the CEO of Business Leadership South Africa.

News24 encourages freedom of speech and the expression of diverse views. The views of columnists published on News24 are therefore their own and do not necessarily represent the views of News24.

View the original on News24 →

KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.