The Jerusalem PostIsraeli man detained in India for carrying live cartridge of ammunition leftover from IDF serviceESPNHow ChatGPT and Lane Kiffin could have gotten LSU kicked out of the SECInquirerBukidnon school eyes safety upgrades after Grade 12 student’s deathPunchEXPLAINER: What every business should know about CAC annual returnsוואלהצה"ל: חוסל מחבל נוח'בה שפשט למעבר ארז ב-7 באוקטוברUN NewsYemen escalation displaces more than 57,000 children: UNICEFBollywood HungamaLuv Ranjan unveils first look of Pehla Pyaar Doosri Baar featuring six debutants, film to release on October 23Premium TimesNIDCOM says Nigerian detained in India refused opportunity to returnIl Fatto Quotidiano“Non so quanto tempo avrò”: Il calcio dominante di Amorim al Milan non si vede. San Siro fischia, ora l’allenatore è preoccupatoCapital FMNyamira University Set for First Intake as Construction ProgressesБи-би-си«Нарисованные победы». Как российские военные с помощью ИИ имитирует успехи на фронте7sur7Menaces de Trump: “Personne” ne dicte au Canada avec quels pays il peut conclure des accords, riposte Carney
The Daily Newsstand · Free, Always
Thursday, September 17, 2026

North-South Commuter Railway full operations moved to Q3 of 2033

Translate

MANILA, Philippines — The scheduled full operation of the North-South Commuter Railway (NSCR) has been moved from 2032 to 2033 due to cost-cutting measures of the government, Palace press officer Claire Castro announced on Thursday.

She said the adjustment was approved by the Economy and Development Council (EDC), chaired by President Ferdinand Marcos Jr., during Wednesday afternoon’s meeting in Malacañang.

“Nagkaroon ng kaunting pagbabago tungkol sa timeline, dahil alam naman natin na nagkaroon ng medyo pagtitipid, mag-iingat  sa pondo ng bayan at nahirapan sa mga procurements and maliban pa diyan ay nagkakaroon ding isyu sa right of way,” Castro said in a briefing.

Article continues after this advertisement

READ: North-South railway on track

FEATURED STORIES

NEWSINFO

NEWSINFO

NEWSINFO

(There have been some adjustments to the timeline, given the need for fiscal prudence and careful management of public funds, as well as challenges regarding procurement and right-of-way issues.)

Based on the new timeline, the first partial operation of the approximately 147 kilometers long NSCR will be in December 2027, while the second partial operation from Malolos to Clark will be in the fourth quarter of 2028.

Meanwhile, the third partial operation of the Clark-Solis and Alabang to Calamba will be in the fourth quarter of 2031, and the full operation of the Clark-Calamba will be in the third quarter of 2033.

“So, usually ang mga amendments nito ay iyong mga timelines lang at medyo may pag-a-adjust din nang kaunti sa budget,” the Palace official explained.

Article continues after this advertisement

(So, usually, the amendments to this involve only the timelines and some slight adjustments to the budget.)

“So, iyong iba ay naaprubahan na, maliban nga doon sa isyu ng pagpapa-announce or paga-announce kung papaano kapag may ulan or mayroong mga ibang causes para ma-suspend ang classes or mga trabaho,” Castro added.

Article continues after this advertisement

(So, some of them have already been approved, except for the issue regarding the announcement—or how announcements are made—when there is rain or other causes for the suspension of classes or work.)

Aside from the NSCR project, the EDC also discussed in their meeting public-private partnership projects such as the Mactan-Cebu International Airport PPP project and the Supporting Innovation in the Philippine Technical and Vocational Education and Training System Project, as well as the Road Network Development Project in conflict-affected areas in Mindanao. /mr