CNN TürkYeni "James Bond" belli olduPunchPlateau newlyweds die in fire, probe beginsInquirerCebu archbishop questions PH participation in Pax SilicaThe Jerusalem PostIDF investigating reported attempted attack near Jericho, military says매일경제화인베스틸, 3분기 누적 영업익 34억…조선업 호황 힘입어 ‘흑자 전환’The Indian ExpressJimmy Tata: Why Ratan Tata’s reclusive brother is at odds with Noel TataDaily MailAmerica plunged into more chaos as United flights are grounded over computer outage just days after nationwide ground stopInfobaeSindicato de la UNP cuestionó a Daniel Briceño tras el asesinato de un escolta en Norte de Santander: “Le falta un grado de respeto”New Straits TimesRinggit opens marginally higher ahead of Q3 GDP dataThe Sydney Morning HeraldRobert Pattinson could make James Bond a little freaky. I’m here for it自由時報急診醫師喊住院 小彤驚嚇像小孩聽到虎姑婆秒變乖La NaciónJavier Milei y sus medidas, en vivo: “Se terminó la mentira del Estado en la Argentina”, dijo el Presidente
The Daily Newsstand · Free, Always
Tuesday, November 17, 2026

Biggest US power grid proposes plan to regulators to cut wait times for data center power

Translate

NEW YORK: The biggest US electric grid operator, PJM Interconnection, said on Monday it is proposing a plan to federal energy regulators to speed up the connection of power plants and the energy-intensive data centers that need them, but the proposal may require data center companies to pay a larger share of grid costs.

PJM Interconnection, which covers 13 US Mid-Atlantic and Midwest states, has struggled to keep up with the rising electricity needs brought by Big Tech's rapid data center expansion that began roughly three years ago.

That supply and demand crunch has triggered a sharp rise in power bills in a region covering 67 million Americans and a roughly 6.8 gigawatt electricity supply shortfall that threatens the reliability of the grid if new power supplies are not secured on time.

PJM, in its proposal to the Federal Energy Regulatory Commission, wants to combine its separate processes of studying the connection of power generation, transmission and large loads like data centers.

The length of the study process, which is required before hooking up a power plant or large data center to the grid, would be reduced to 12 months from two years, PJM said.

"Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by large loads like data centers," said PJM spokesman Jeff Shields.

"The factor that PJM planning can influence is how quickly these new resources are studied for reliability."

By combining the planning process, PJM said it would also be able to identify exactly how and where the grid will need upgrades to accommodate new data centers.

That, PJM said, will give states and utilities clear information about the transmission costs driven by data centers and allow them to bill the companies directly instead of spreading the costs across other users.

Data center advocates have pushed back against earlier discussions of the combined study process, with the trade group Data Center Coalition telling the PJM board in October that the combined process might complicate the grid interconnection process and ultimately lead to longer delays in connecting power plants and data centers.

PJM is asking that FERC begin a 60-day comment period on its proposed plan and issue a ruling within 120 days. — REUTERS

View the original on New Straits Times →