Sabah Electricity sets 6-day target to restore normal power supply

Sabah Electricity Sdn Bhd has set a six-day target to restore the 275-kilovolt (kV) transmission line to Sabah’s east coast after a transmission tower toppled in Ranau today.
Its chairman, Saadiah Aziz, said full restoration of supply and the electricity grid is expected on Dec 2 once the two affected transmission lines are reconnected.
She said the six-day timeframe is also needed for Sabah Electricity and its contractors to deliver equipment to erect a temporary tower and reconnect the affected lines at a safe location, near where the earlier structure toppled.
“We are targeting six days to reconnect the affected grid; it might even be completed earlier,” she told a press conference at Sabah Electricity headquarters here tonight.
She said they activated their crisis management system immediately upon identifying the cause of the disruption and arranged urgent steps to temporarily restore supply in affected districts.
The outage affected 153,599 registered consumers.
Saadiah said Sabah Electricity personnel first cleared the main Ranau-Telupid road of hanging cables before carrying out emergency power restoration in stages.
Throughout the restoration period, she said electricity supply on Sabah’s east coast would be generated using existing power stations in Sandakan and Tawau, supported by mobile generators sent to all affected areas.
“Sabah Electricity has succeeded in linking the east coast grid lines, boosting supply capacity and limiting electricity rationing to between one and two hours,” she said.
Transmission tower T313 in Ranau toppled early this morning, affecting both transmission line circuits and disrupting electricity supply to Sabah’s east coast.
Eight districts experienced a power outage at 6.04am.
KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.