PunchLawyer faults Akpabio over jail term view for suicide survivorsThe Jerusalem PostIran tensions, Syria talks put Iraqi Kurdistan at the center of Middle Eastern diplomacy - analysisBollywood HungamaEXCLUSIVE: Rohit Shetty-backed Krithi Shetty-starrer titled Hum Tere Pyaar Mein; to be directed by his protégé Vidhi GhodgaonkarESPN'We're a really hard team to beat': Brewers prove their way can take down anyoneRTP DesportoMundial de Hóquei. Portugal defronta Itália após desaire com EspanhaInquirerGroup backs MILF’s Ebrahim as new BARMM gov’t headZDF heuteEntdecken Sie das ZDF-NachrichtenstudioIl Fatto QuotidianoPedro Sanchez risponde a Luciana Littizzetto: “Io in Italia a guidare il campo largo? Devo rimanere il Spagna a cucinare paella per almeno quattro anni. Sempre tuo, Pedro Pedro Pedro”Daily MailRussell Brand trial latest updates: Comedian 'is a ruthless and manipulative sexual predator with a voracious sexual appetite', and told friend he 'wanted to bed 5,000 women in his lifetime', court hearsTagesschauVerurteilter Signa-Gründer Benko darf in den Hausarrest wechselnn-tvAngreifer verfasste Manifest: Polizei stuft Schulattacke in Schongau als rechte Gewalttat einالشرقاليابان تعتزم استدعاء سفير روسيا بعد اعتقال صحافي بتهمة التجسس
The Daily Newsstand · Free, Always
Wednesday, October 14, 2026

Test flights check navigation systems ahead of Long Thanh airport's imminent opening

Translate

Test and calibration flights on Oct. 12 and 13 checked navigation systems and signal lights at the under-construction Long Thanh International Airport in Dong Nai City.

The flight inspection and calibration center run by the Air Traffic Technical Co. Ltd (Attech) used a Beechcraft B300/B350 to inspect systems serving runway 05R/23L.

Attech is a subsidiary of the state-owned Vietnam Air Traffic Management Corporation.

Unlike transport planes, calibration aircraft follow specially designed flight paths to test the technical parameters of navigation systems and signal lights.

They approach along the runway center line, fly predetermined trajectories and perform specific maneuvers to assess equipment coverage and accuracy.

Máy bay Beechcraft B300/B350 chuẩn bị cất cánh từ sân bay Tân Sơn Nhất, để bay kiểm tra, hiệu chuẩn các hệ thống dẫn đường và đèn tín hiệu hàng không tại sân bay Long Thành. Ảnh: Phương Linh

A Beechcraft B300/B350 aircraft prepares to take off from Tan Son Nhat International Airport for a flight to inspect and calibrate navigation systems and aeronautical lighting at Long Thanh International Airport. Photo by Phuong Linh

Evaluation of the systems used for navigation, approach, and landing is mandatory before Long Thanh Airport begins operations.

On Oct. 12, the aircraft tested the instrument landing system and distance measuring equipment (ILS/DME), precision approach path indicator (PAPI) lights and radio navigation systems.

On Oct. 13, the ILS/DME was again tested as was the approach lighting system (ALS).

ILS/DME provides guidance and distance information, helping pilots determine their approach path to the runway.

PAPI lights help pilots identify the correct approach angle through visual light signals, while the ALS helps pilots identify the runway and orient themselves as they transition to the visual approach phase.

Through these flights, technical teams collected data to assess the accuracy and operational performance of each system in real-world conditions, and this will provide a basis for further technical preparations at the airport.

Calibration flights require controllers to have a thorough understanding of each flight procedure, maintain continuous communication and coordinate precisely with flight crews and ground technical teams.

Phi công theo dõi, điều khiển tàu bay thực hiện các bài bay kiểm tra, hiệu chuẩn hệ thống dẫn đường và đèn tín hiệu hàng không tại Cảng HKQT Long Thành. Ảnh: Phương Linh

Pilots monitor and control aircraft during test flights to inspect and calibrate navigation systems and aeronautical lighting at Long Thanh International Airport. Photo by Phuong Linh

According to the Vietnam Air Traffic Management Corporation, the tests also help assess the coordination between air traffic control facilities, technical conditions, and the readiness of air traffic control and meteorological personnel at the airport.

Long Thanh is slated to open in late 2026.

The 5,000-hectare airport cost nearly US$16 billion to build. In its first phase, it will have one runway and passenger terminal each and an annual capacity of 25 million passengers and 1.2 million tons of cargo.

Along with Tan Son Nhat airport in Ho Chi Minh City, it will serve as the aviation gateways for the region, helping ease congestion at the existing airport and enable more international flights and cargo transport.

View the original on VnExpress International →