Punch2027: Northern candidates should wait till 2031 to contest – Kano govThe Jerusalem Post'I'm responsible for hell': Ben-Gvir threatens Hamas terrorist behind 1996 bus bombingsDaily MaverickGROUNDUP: Gauteng government’s R144m gift to beauty training companyBollywood HungamaAnshuman Jha plans special screenings of Om Ka Hari across 15 cities as film enters week 2: "I want to keep walking that extra mile"Inquirer6 fugitives arrested in Northern MindanaoVarietyFlorence Pugh Speaks Out Over Cornell University Sexual Assault Case: ‘We Need Our Men to Be as Horrified and Sickened as Us’CNN TürkEnner Valencia'dan hat-trick! 3 golle skoru değiştirdiUOLColaboradora de María Corina Machado retorna à VenezuelaХабр«Мы больше не можем это взломать»: как Anthropic похоронила промпт-инъекции, но забыла про особенности AI-агентовNOSGezinsdrama in Vlaanderen, zoon (17) verdacht van moord op moeder en zusWirtualna PolskaTak mieli zarobić miliony. Kradli auta i rozkładali je na części7sur7Pourquoi l’hérédité ne dépend pas uniquement de l’ADN
The Daily Newsstand · Free, Always
Monday, September 28, 2026

Visayas grid under yellow alert on September 28, 2026 --NGCP

Translate

Make this your preferred source to get more updates from this publisher on Google.

The Visayas grid will again be placed under yellow alert on Monday, September 28, due to tight energy reserves, the National Grid Corporation of the Philippines (NGCP) said.

In an advisory, the NGCP said the yellow alert status will be in effect between 5 p.m. to 7 p.m.

The grid is currently running on an available capacity of 2,572 megawatts (MW) although the peak demand is 2,374 MW.

The yellow alert status declaration is due to the unavailability of Visayas' large coal plants: Panay Energy Development Corporation Unit 3, KEPCO SPC Power Corporation Unit 2, and Therma Visayas Inc. Unit 1. The said plants were shut down at 4:34 a.m.

Meanwhile, 14 plants are on forced outage on September, three plants since August, two plants since June, six plants since May, three plants since 2025, two plants since 2024, two plants since 2023, and one plant since 2021. There are also 15 plants are running on derated capacities, for a total of 928.3MW unavailable to the grid.

A yellow alert is issued when the operating margin is insufficient to meet the transmission grid’s contingency requirement.

To address the thinning energy reserves in the Visayas grid, the Department of Energy (DOE) earlier ordered the NGCP to install over 250 megawatts of battery energy storage system.

The DOE is also mulling to tap liquid fuel facilities to help power up the grid. —Vince Angelo Ferreras/KG, GMA News