The Jerusalem PostIDF launches mentorship program to integrate discharged haredi soldiers into high-tech sectorInquirerFire kills 1, leaves families homeless in Sta. Mesa, ManilaPunchSmart devices redefining music entertainmentCNN TürkBUDO HANGİ SEFERLER İPTAL EDİLDİ? 23 Kasım Bursa Deniz Otobüsleri son durum nedir?한겨레스트레이 키즈 필릭스 ‘한복웨이브’ 화보 서울역에 뜬다ZDF heuteEntdecken Sie das ZDF-NachrichtenstudioThe Sydney Morning HeraldBeau Lamarre-Condon trial live updates: Defence closing address set to start after Crown address concludes매일경제靑재정보좌관 “증시 충격 일시적일 수 있어…비관적으로 안 봐”경향신문올해 최고 울산시정은?···다음 달 4일까지 시민 대상 설문조사Daily MailRise of the robopets! In a disturbing trend, Gen Z are rejecting relationships and babies in favour of looking after cute, AI-powered toys that 'offer healing and comfort'ESPN DeportesAsí vivieron los aficionados la previa del partidoNew Straits TimesLeaders Barcelona make impressive Villarreal comeback, Atletico triumph
The Daily Newsstand · Free, Always
Monday, November 23, 2026

부산도시공사, 센텀2지구 풍산 부산사업장 토지 보상 착수

Translate
오수희

이미지 확대 부산 센텀2지구 예정지

부산 센텀2지구 예정지

연합뉴스 자료 사진

(부산=연합뉴스) 오수희 기자 = 부산도시공사는 센텀2지구 도시첨단산업단지 조성사업에 편입된 풍산 부산사업장 토지에 대한 보상계획을 공고했다고 23일 밝혔다.

공고 대상은 해운대구 반여동·반송동 일원 풍산 소유 토지 약 100만㎡다.

이는 센텀2지구 전체 면적(약 191만㎡)의 절반을 넘는 규모다.

공사는 2023년 6월 풍산 용지 등을 제외한 일반 사유지에 대해 보상을 착수해 올해 9월 손실보상(토지·지장물 등)을 대부분 끝냈다.

공사는 풍산 부산사업장의 이전 일정을 고려해 토지를 우선 보상하기로 했다.

건축물과 생산설비 등 물건에 대한 보상계획은 이전 시기에 맞춰 별도로 공고할 예정이다.

공고와 토지조서 열람 기간은 이날부터 12월 11일까지다.

공사는 열람이 끝나면 감정평가법인 선정과 감정평가를 거쳐 2027년 3월 보상 협의를 시작할 계획이다.

공고문은 일간신문과 공사 홈페이지(www.bmc.busan.kr)에 게재된다.

신창호 부산도시공사 사장은 "풍산 부산사업장 토지 보상은 센텀2지구 조성사업의 가장 큰 관문"이라며 "관계 법령에 따라 공정하고 투명하게 보상 절차를 진행하겠다"고 말했다.

osh9981@yna.co.kr

제보는 카카오톡 okjebo <저작권자(c) 연합뉴스, 무단 전재-재배포, AI 학습 및 활용 금지> 2026년11월23일 08시33분 송고