CNN TürkJP Morgan’dan altın için yeni tahmin! 2027'de ne olacak?Daily MaverickEDUCATION: Apply matric strategy to learners from Grade 1 onwardsPunchKano deploys over 1,000 forest guards to tackle insecurityThe Jerusalem PostTwice in 24 hours: IDF intercepts balloons carrying drugs across Egyptian border over weekend한겨레한준호 잦은 주소 이전, 강유정 보좌진 전별금…청문회 검증 쟁점InquirerNat’l funds must be for priorities identified by local communities—Speaker Dyהידעןאיך חיידקים מייצרים תרופה נגד סרטן בלי להיפגע ממנה? התגלה החלבון שמגן עליהםHipertextualAsí es AtlasOS, la versión de Windows que elimina lo que nadie usa y acelera tu PCWirtualna Polska"Ograniczenia powinny zostać zniesione". Szef BBN o reakcji na rosyjskie rakiety nad PolskąKoimoiGunmaaster G9 Box Office Day 2: Grows By 19% On Saturday, Becomes Highest-Grossing Collaboration Between Emraan Hashmi & Aditya DattSözcüKubilay Kaan Kundakçı cinayetinde karar istinafa taşındı, baba konuştu: "En büyük suçlu Aleyna"Bollywood HungamaYeh Prem Mol Liya Box Office Day 3 Advance Booking: Ayushmann Khurrana-Sooraj Barjatya film sells over 1.12 lakh tickets; Sunday advance hits Rs. 2.85 crores
The Daily Newsstand · Free, Always
Sunday, November 29, 2026

You are reading Free Malaysia Today on KioskNews: newspapers from many countries on one stand, each linked to its original. What other papers report

Miri Trans Borneo Highway project due by end of 2029, says Nanta

Translate

The Miri section of the Trans Borneo Highway (LTB), costing RM136.1 million, is expected to be completed by October 2029.

It will increase road capacity from the Kuala Baram junction to the Sungai Tujuh Immigration, Customs, Quarantine and Security (ICQS) Complex.

Works minister Alexander Nanta Linggi said the project involved upgrading 4.9km of road, comprising 4.1km in Section I and 0.8km in Section II.

“The existing single-carriageway, two-lane road will be upgraded to a dual carriageway with four lanes in both directions.

“The project includes improvements to the existing roundabout before the Sungai Tujuh ICQS. The new, more efficient roundabout design will meet the requirements of an R5-standard dual carriageway and is expected to improve traffic flow to the border crossing,” he said after the groundbreaking ceremony for the Miri section of the LTB and the Miri Redline Short Stretch project here today.

Nanta said the LTB project comprised three main sections, Miri, Limbang and Lawas, covering a total of 93km to complement the Pan Borneo Highway and the Sarawak-Sabah Link Road (SSLR).

The Sarawak public works department (JKR) has completed its evaluation of tenders for the Limbang and Lawas sections.

The results will be submitted to the works ministry’s procurement board for recommendations before being referred to the finance ministry for approval, he said.

Letters of acceptance for the two sections are expected to be issued in the first quarter of 2027, with each section having a construction period of three years.

Meanwhile, the Redline Short Stretch project involves road upgrades at nine locations in Sarawak, covering a total of 17.1km, including the Tudan section of the Miri-Kuala Baram route.

Nanta said the project had been approved under a RM119.7 million contract, with the Tudan section scheduled for completion in January 2028.

“When both projects are completed, travel from southern and central Sarawak to Miri, and from Miri to the border crossing, is expected to be smoother. Road and junction upgrades on the route to the Sungai Tujuh ICQS are also expected to ease congestion, especially during peak hours.

“With smoother routes, goods can be transported more easily between Miri and Brunei Darussalam. This can boost tourism and cross-border trade, creating more business opportunities for hoteliers, tour operators and small and medium-sized traders in Miri,” he said.