Miri Trans Borneo Highway project due by end of 2029, says Nanta
The Miri section of the Trans Borneo Highway (LTB), costing RM136.1 million, is expected to be completed by October 2029.
It will increase road capacity from the Kuala Baram junction to the Sungai Tujuh Immigration, Customs, Quarantine and Security (ICQS) Complex.
Works minister Alexander Nanta Linggi said the project involved upgrading 4.9km of road, comprising 4.1km in Section I and 0.8km in Section II.
“The existing single-carriageway, two-lane road will be upgraded to a dual carriageway with four lanes in both directions.
“The project includes improvements to the existing roundabout before the Sungai Tujuh ICQS. The new, more efficient roundabout design will meet the requirements of an R5-standard dual carriageway and is expected to improve traffic flow to the border crossing,” he said after the groundbreaking ceremony for the Miri section of the LTB and the Miri Redline Short Stretch project here today.
Nanta said the LTB project comprised three main sections, Miri, Limbang and Lawas, covering a total of 93km to complement the Pan Borneo Highway and the Sarawak-Sabah Link Road (SSLR).
The Sarawak public works department (JKR) has completed its evaluation of tenders for the Limbang and Lawas sections.
The results will be submitted to the works ministry’s procurement board for recommendations before being referred to the finance ministry for approval, he said.
Letters of acceptance for the two sections are expected to be issued in the first quarter of 2027, with each section having a construction period of three years.
Meanwhile, the Redline Short Stretch project involves road upgrades at nine locations in Sarawak, covering a total of 17.1km, including the Tudan section of the Miri-Kuala Baram route.
Nanta said the project had been approved under a RM119.7 million contract, with the Tudan section scheduled for completion in January 2028.
“When both projects are completed, travel from southern and central Sarawak to Miri, and from Miri to the border crossing, is expected to be smoother. Road and junction upgrades on the route to the Sungai Tujuh ICQS are also expected to ease congestion, especially during peak hours.
“With smoother routes, goods can be transported more easily between Miri and Brunei Darussalam. This can boost tourism and cross-border trade, creating more business opportunities for hoteliers, tour operators and small and medium-sized traders in Miri,” he said.