ESPN DeportesLeón venció al Atlético de San Luis con doblete de CambindoESPNJudge hits 1st HR since May as Yankees clinch record 61st postseason spotCNN TürkFatih'te daha önce kurşunlanan iş yerinin fotoğraflarını çeken şüpheli tutuklandıPunchRansom economy: How kidnappers turn northern families’ pain into profitוואלהגבר כבן 70 נפצע קשה באשקלוןInquirerLOOK: DILG releases new mugshots of RomualdezUOLParte do Vale do Silício vê interesse comercial por trás de discurso de segurança e desaceleração da IAالشرقالمحكمة العليا ترفض خطة ترمب للحد من التصويت بالبريد في انتخابات التجديد النصفيNew Straits TimesCar crashes into elephant on Jalan Jerangau-Jabor, 3 people injuredThe Hollywood Reporter‘The Pitt’ Showrunner R. Scott Gemmill Delivers Rallying Cry for “What’s Real” After Emmy WinDaily MailEmmy Awards 2026 best dressed! Zendaya, Selena Gomez and Mariska Hargitay lead red carpet glamour at TV's biggest nightThe GuardianEmmy awards 2026 live: The Pitt wins best drama as Widow’s Bay cleans up comedy categories
The Daily Newsstand · Free, Always
Tuesday, September 15, 2026

「做好了卻不能搭?」苗栗車站6座電扶梯完工 台鐵回應了

Translate

根據「電腦網路內容分級處理辦法」修正條文第六條第三款規定,已於網站首頁或各該限制級網頁,依台灣網站分級推廣基金會規定作標示。 台灣網站分級推廣基金會(TICRF)網站:http://www.ticrf.org.tw

台鐵苗栗車站增設6座電扶梯,主體工程已於今年9月2日完竣。(記者彭健禮攝)

台鐵苗栗車站增設電扶梯工程,已施工近2年,旅客發現電扶梯已設置完成,卻遲遲不見啟用。立委沈發惠追蹤關心,台鐵公司回覆表示申辦使用執照取得、消防竣工查驗及升降設備許可證核發等法定程序中,力求今年12月底前啟用開放。

台鐵苗栗車站為跨站式站房,售票口及進、出站匣門在3樓,旅客搭車要先上3樓再下1樓月台,雖設有4座電梯,但沒有電扶梯,屢遭民眾投訴抱怨動線不友善長者及身障者。

沈發惠接獲地方陳情,於2023年9月由苗栗辦公室團隊、縣議員徐筱菁,與台鐵公司人員會勘,台鐵提具「苗栗站增設電扶梯及既有雨遮整建工程」,並編列1億700多萬元經費,在車站東站側現有出入口階梯旁及第一、第二月台,分別增設上、下各一座電扶梯,共計6座,另改善第一月台的雨遮設施。工程於2024年10月開工。

沈發惠辦公室追蹤關心,台鐵回覆表示此案主體工程已於今年9月2日完竣,現辦理後續使用執照取得、消防竣工查驗及升降設備許可證核發等法定程序,目前皆已完成掛件,由地方政府執照核發主管單位作業程序中,台鐵將全力加速各項行政作業,力求於今年12月底前全面完成相關啟用程序並開放使用。